Modular DIN-Rail Industrial Safety PLC I/O
Product family: SIL-3 Analog/Digital Bricks.
Flow: DIN-Rail Housing Suppliers → Dual-Side SMT & AOI → DIN Spring-Cage Wave Solder → Robotic Housing Snap-Fit → CANopen / Profinet Flash → HIL Channel Fault Inject QC → Factory Automation Integrators
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Dual-Side SMT & AOI | 15.9 s | 25 min | 95% | 98.6% | 1,520 | 2,280 (1.20 d) | 3,071 |
| 2. DIN Spring-Cage Wave Solder | 23.3 s | 35 min | 91% | 97.4% | 1,520 | 2,660 (1.40 d) | 1,954 |
| 3. Robotic Housing Snap-Fit | 30.4 s | 45 min | 84% | 95.4% | 1,900 | 3,420 (1.80 d) | 1,352 |
| 4. CANopen / Profinet Flash | 22.2 s | 18 min | 93% | 98.1% | 760 | 1,900 (1.00 d) | 2,108 |
| 5. HIL Channel Fault Inject QC | 19.3 s | 15 min | 95% | 98.8% | 475 | 1,520 (0.80 d) | 2,451 |
Key figures
- Takt time
- 28.4 s
- Lead time
- 7.40 d
- Value-added time
- 111 s
- Process cycle efficiency (PCE)
- 0.028%
- Rolled throughput yield (RTY)
- 88.8%
- Customer demand per day
- 1,900 units
- Line capacity per day
- 1,352 units
- Bottleneck
- Robotic Housing Snap-Fit
Reading the bottleneck
The bottleneck is "Robotic Housing Snap-Fit": it can process 1,352 units per day against a demand of 1,900 units, so it falls short of demand by 28.8%. Once downtime and scrap are counted, its cycle time grows from 30.4 s to 37.9 s, against a takt of 28.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 5.8 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of PCB SMT & Box-Build EMS: PCB SMT & Box-Build EMS
- PCB SMT Pick-and-Place & Box Build
- Automotive ASIL-D EV BMS Mainboard SMT
- 64T64R 5G Massive-MIMO Antenna PCB Line
- 77GHz Automotive ADAS Radar Sensor PCB
- ISO-13485 Medical Ultrasound Beamformer PCB
- Dual-Socket AI GPU Server Motherboard
- NB-IoT Ultrasonic Smart Water/Gas Meter
- Three-Phase Industrial VFD Inverter Gate Board
- PCI-PTS Secure EMV Payment Terminal PCBA
- Matter & Thread Smart Home Gateway Line
- Rigid-Flex Polyimide Satellite Bus Board