Matter & Thread Smart Home Gateway Line
Product family: Consumer IoT Bridges.
Flow: RF SoC Suppliers → High-Speed Chip Mounter → Shield-Can Snap & Reflow → Snap Case & Laser Barcode → Wi-Fi / Matter Throughput OTA → Auto Carton Sleeve Weight → Telecom & Smart Retail
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. High-Speed Chip Mounter | 8.4 s | 25 min | 95% | 98.6% | 2,880 | 4,320 (1.20 d) | 5,813 |
| 2. Shield-Can Snap & Reflow | 12.3 s | 35 min | 91% | 97.4% | 2,880 | 5,040 (1.40 d) | 3,702 |
| 3. Snap Case & Laser Barcode | 16.1 s | 45 min | 84% | 95.4% | 3,600 | 6,480 (1.80 d) | 2,553 |
| 4. Wi-Fi / Matter Throughput OTA | 11.7 s | 18 min | 93% | 98.1% | 1,440 | 3,600 (1.00 d) | 4,000 |
| 5. Auto Carton Sleeve Weight | 10.2 s | 15 min | 95% | 98.8% | 900 | 2,880 (0.80 d) | 4,638 |
Key figures
- Takt time
- 15.0 s
- Lead time
- 7.40 d
- Value-added time
- 58.7 s
- Process cycle efficiency (PCE)
- 0.015%
- Rolled throughput yield (RTY)
- 88.8%
- Customer demand per day
- 3,600 units
- Line capacity per day
- 2,553 units
- Bottleneck
- Snap Case & Laser Barcode
Reading the bottleneck
The bottleneck is "Snap Case & Laser Barcode": it can process 2,553 units per day against a demand of 3,600 units, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 16.1 s to 20.1 s, against a takt of 15.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 3.1 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of PCB SMT & Box-Build EMS: PCB SMT & Box-Build EMS
- PCB SMT Pick-and-Place & Box Build
- Automotive ASIL-D EV BMS Mainboard SMT
- 64T64R 5G Massive-MIMO Antenna PCB Line
- 77GHz Automotive ADAS Radar Sensor PCB
- ISO-13485 Medical Ultrasound Beamformer PCB
- Dual-Socket AI GPU Server Motherboard
- NB-IoT Ultrasonic Smart Water/Gas Meter
- Three-Phase Industrial VFD Inverter Gate Board
- Modular DIN-Rail Industrial Safety PLC I/O
- PCI-PTS Secure EMV Payment Terminal PCBA
- Rigid-Flex Polyimide Satellite Bus Board