Rigid-Flex Polyimide Satellite Bus Board

Product family: Radiation-Tolerant Flex PCBs.

Flow: Polyimide flex laminate supplier → Vacuum Bakeout & Paste Print → IPC Class-3 SMD Placement → Vapor Phase Reflow & Wash → RTV Silicone Vibration Stake → Thermal Shock & Flying Probe → Space & Defense Primes

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Rigid-Flex Polyimide Satellite Bus BoardSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Polyimide flex laminate supplier → Vacuum Bakeout & Paste Print (336 s) → IPC Class-3 SMD Placement (492 s) → Vapor Phase Reflow & Wash (642 s) → RTV Silicone Vibration Stake (468 s) → Thermal Shock & Flying Probe (408 s) → Space & Defense Primes.SUPPLIERPolyimide flexlaminatesupplierI1.20 d1Vacuum Bakeout &Paste PrintC/T 336 sI1.40 d2IPC Class-3 SMDPlacementC/T 492 sI1.80 d3Vapor PhaseReflow & WashC/T 642 sI1.00 d4RTV SiliconeVibration StakeC/T 468 sI0.80 d5Thermal Shock &Flying ProbeC/T 408 sI1.20 dCUSTOMERSpace & DefensePrimes45 / boards

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Vacuum Bakeout & Paste Print336 s25 min95%98.6%3654 (1.20 d)70
2. IPC Class-3 SMD Placement492 s35 min91%97.4%3663 (1.40 d)44
3. Vapor Phase Reflow & Wash642 s45 min84%95.4%4581 (1.80 d)30
4. RTV Silicone Vibration Stake468 s18 min93%98.1%1845 (1.00 d)47
5. Thermal Shock & Flying Probe408 s15 min95%98.8%1136 (0.80 d)54

Key figures

Takt time
600 s
Lead time
7.49 d
Value-added time
2,346 s
Process cycle efficiency (PCE)
1.2%
Rolled throughput yield (RTY)
88.8%
Customer demand per day
45 boards
Line capacity per day
30 boards
Bottleneck
Vapor Phase Reflow & Wash

Reading the bottleneck

The bottleneck is "Vapor Phase Reflow & Wash": it can process 30 boards per day against a demand of 45 boards, so it falls short of demand by 32.6%. Once downtime and scrap are counted, its cycle time grows from 642 s to 801 s, against a takt of 600 s. The largest loss at this step is equipment downtime (uptime 84%), about 122 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.