Modular 1MW Online Double-Conversion UPS
Product family: 97.5% Eco-Mode Data Center UPS.
Flow: IGBT Stacks & Fan Trays → 2m Heavy Cabinet Frame Build → Backplane Busbar & Bypass → Hot-Swap Inverter Brick Test → CAN Sync Master Display Wire → 1MW Step-Load Battery Burn → Tier-IV Cloud Data Centers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 2m Heavy Cabinet Frame Build | 3,060 s | 25 min | 95% | 99.1% | 12 | 20 (1.67 d) | 16 |
| 2. Backplane Busbar & Bypass | 3,510 s | 20 min | 93% | 98.4% | 7 | 18 (1.50 d) | 14 |
| 3. Hot-Swap Inverter Brick Test | 4,860 s | 18 min | 86% | 95.8% | 5 | 24 (2.00 d) | 9 |
| 4. CAN Sync Master Display Wire | 3,600 s | 12 min | 93% | 97.6% | 3 | 13 (1.08 d) | 13 |
| 5. 1MW Step-Load Battery Burn | 2,880 s | 10 min | 96% | 99.0% | 2 | 10 (0.83 d) | 17 |
Key figures
- Takt time
- 4,500 s
- Lead time
- 8.83 d
- Value-added time
- 17,910 s
- Process cycle efficiency (PCE)
- 3.8%
- Rolled throughput yield (RTY)
- 90.3%
- Customer demand per day
- 12 units
- Line capacity per day
- 9 units
- Bottleneck
- Hot-Swap Inverter Brick Test
Reading the bottleneck
The bottleneck is "Hot-Swap Inverter Brick Test": it can process 9 units per day against a demand of 12 units, so it falls short of demand by 27.4%. Once downtime and scrap are counted, its cycle time grows from 4,860 s to 5,899 s, against a takt of 4,500 s. The largest loss at this step is equipment downtime (uptime 86%), about 791 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Switchgear, UPS & Power Systems: Switchgear, UPS & Power Systems
- 24kV SF6-Free Gas-Insulated Switchgear Bay
- Withdrawable 4000A Low-Voltage MCC Lineup
- 2.5MVA Cast-Resin Dry Distribution Transformer
- 350kW Liquid-Cooled EV Highway Fast Charger
- Intelligent 42-Breaker Monitored Rack PDU
- 1500V Utility 250kW String Solar Inverter
- IEC-61850 Digital Substation Protection Relay
- 400kWh Grid Liquid-Cooled LFP Battery Rack
- 4000A Solenoid-Operated Automatic Transfer Switch
- Active Harmonic Filter & Capacitor Bank
- Multi-Axis EtherCAT Industrial Servo Drive