Withdrawable 4000A Low-Voltage MCC Lineup

Product family: Smart Motor Control Centers.

Flow: Drawer Unit Suppliers → Main Horizontal Busbar Stack → Withdrawable Drawer Cell Fit → Smart Starter Relay Wiring → Fieldbus Profibus / Ethernet → Secondary Inject & Heat-Rise → Process & Mining Plants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Withdrawable 4000A Low-Voltage MCC LineupSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Drawer Unit Suppliers → Main Horizontal Busbar Stack (1,049 s) → Withdrawable Drawer Cell Fit (1,203 s) → Smart Starter Relay Wiring (1,666 s) → Fieldbus Profibus / Ethernet (1,234 s) → Secondary Inject & Heat-Rise (987 s) → Process & Mining Plants.SUPPLIERDrawer UnitSuppliersI1.71 d1Main HorizontalBusbar StackC/T 1,049 sI1.51 d2WithdrawableDrawer Cell FitC/T 1,203 sI2.00 d3Smart StarterRelay WiringC/T 1,666 sI1.11 d4Fieldbus Profibus/ EthernetC/T 1,234 sI0.80 d5Secondary Inject& Heat-RiseC/T 987 sI1.40 dCUSTOMERProcess &Mining Plants35 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Main Horizontal Busbar Stack1,049 s25 min95%99.1%3560 (1.71 d)47
2. Withdrawable Drawer Cell Fit1,203 s20 min93%98.4%2153 (1.51 d)40
3. Smart Starter Relay Wiring1,666 s18 min86%95.8%1470 (2.00 d)25
4. Fieldbus Profibus / Ethernet1,234 s12 min93%97.6%939 (1.11 d)38
5. Secondary Inject & Heat-Rise987 s10 min96%99.0%728 (0.80 d)49

Key figures

Takt time
1,543 s
Lead time
8.66 d
Value-added time
6,139 s
Process cycle efficiency (PCE)
1.3%
Rolled throughput yield (RTY)
90.3%
Customer demand per day
35 units
Line capacity per day
25 units
Bottleneck
Smart Starter Relay Wiring

Reading the bottleneck

The bottleneck is "Smart Starter Relay Wiring": it can process 25 units per day against a demand of 35 units, so it falls short of demand by 27.5%. Once downtime and scrap are counted, its cycle time grows from 1,666 s to 2,022 s, against a takt of 1,543 s. The largest loss at this step is equipment downtime (uptime 86%), about 271 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.