2.5MVA Cast-Resin Dry Distribution Transformer

Product family: Eco-Design Tier-2 Transformers.

Flow: Grain-Oriented Steel Supplier → Step-Lap Core Stack Assembly → Foil LV & Glass HV Winding → Vacuum Epoxy Casting Cure → Core-Coil Clamp & Bus Risers → No-Load Loss & Lightning Test → Hospitals, Metro & Data Centers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 2.5MVA Cast-Resin Dry Distribution TransformerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Grain-Oriented Steel Supplier → Step-Lap Core Stack Assembly (2,623 s) → Foil LV & Glass HV Winding (3,009 s) → Vacuum Epoxy Casting Cure (4,166 s) → Core-Coil Clamp & Bus Risers (3,086 s) → No-Load Loss & Lightning Test (2,469 s) → Hospitals, Metro & Data Centers.SUPPLIERGrain-OrientedSteel SupplierI1.71 d1Step-Lap CoreStack AssemblyC/T 2,623 sI1.50 d2Foil LV & GlassHV WindingC/T 3,009 sI2.00 d3Vacuum EpoxyCasting CureC/T 4,166 sI1.07 d4Core-Coil Clamp &Bus RisersC/T 3,086 sI0.79 d5No-Load Loss &Lightning TestC/T 2,469 sI1.43 dCUSTOMERHospitals,Metro & Data…14 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Step-Lap Core Stack Assembly2,623 s25 min95%99.1%1424 (1.71 d)19
2. Foil LV & Glass HV Winding3,009 s20 min93%98.4%821 (1.50 d)16
3. Vacuum Epoxy Casting Cure4,166 s18 min86%95.8%628 (2.00 d)10
4. Core-Coil Clamp & Bus Risers3,086 s12 min93%97.6%415 (1.07 d)15
5. No-Load Loss & Lightning Test2,469 s10 min96%99.0%311 (0.79 d)20

Key figures

Takt time
3,857 s
Lead time
8.78 d
Value-added time
15,353 s
Process cycle efficiency (PCE)
3.2%
Rolled throughput yield (RTY)
90.3%
Customer demand per day
14 units
Line capacity per day
10 units
Bottleneck
Vacuum Epoxy Casting Cure

Reading the bottleneck

The bottleneck is "Vacuum Epoxy Casting Cure": it can process 10 units per day against a demand of 14 units, so it falls short of demand by 27.3%. Once downtime and scrap are counted, its cycle time grows from 4,166 s to 5,057 s, against a takt of 3,857 s. The largest loss at this step is equipment downtime (uptime 86%), about 678 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.