IEC-61850 Digital Substation Protection Relay

Product family: Differential Line Relays.

Flow: Al Extrusion & Optical IO → Input CT/VT Magnetics Wind → Ruggedized Backplane SMT → Chassis Card Slide & Gasket → IEC-61850 Goose Stack Flash → Relay Test-Set Trip Sweep → HV Transmission Utilities

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: IEC-61850 Digital Substation Protection RelaySupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Al Extrusion & Optical IO → Input CT/VT Magnetics Wind (262 s) → Ruggedized Backplane SMT (301 s) → Chassis Card Slide & Gasket (417 s) → IEC-61850 Goose Stack Flash (309 s) → Relay Test-Set Trip Sweep (247 s) → HV Transmission Utilities.SUPPLIERAl Extrusion &Optical IOI1.70 d1Input CT/VTMagnetics WindC/T 262 sI1.50 d2RuggedizedBackplane SMTC/T 301 sI2.00 d3Chassis CardSlide & GasketC/T 417 sI1.10 d4IEC-61850 GooseStack FlashC/T 309 sI0.80 d5Relay Test-SetTrip SweepC/T 247 sI1.40 dCUSTOMERHV TransmissionUtilities140 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Input CT/VT Magnetics Wind262 s25 min95%99.1%140238 (1.70 d)189
2. Ruggedized Backplane SMT301 s20 min93%98.4%84210 (1.50 d)158
3. Chassis Card Slide & Gasket417 s18 min86%95.8%56280 (2.00 d)101
4. IEC-61850 Goose Stack Flash309 s12 min93%97.6%35154 (1.10 d)150
5. Relay Test-Set Trip Sweep247 s10 min96%99.0%28112 (0.80 d)196

Key figures

Takt time
386 s
Lead time
8.53 d
Value-added time
1,536 s
Process cycle efficiency (PCE)
0.33%
Rolled throughput yield (RTY)
90.3%
Customer demand per day
140 units
Line capacity per day
101 units
Bottleneck
Chassis Card Slide & Gasket

Reading the bottleneck

The bottleneck is "Chassis Card Slide & Gasket": it can process 101 units per day against a demand of 140 units, so it falls short of demand by 27.6%. Once downtime and scrap are counted, its cycle time grows from 417 s to 506 s, against a takt of 386 s. The largest loss at this step is equipment downtime (uptime 86%), about 67.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.