400kWh Grid Liquid-Cooled LFP Battery Rack
Product family: UL-9540A BESS Modules.
Flow: 314Ah LFP Cell Plants → Module Glycol Tray Bond → 314Ah Cell Laser Strapping → Rack String BMS & Pyro Fuse → Glycol Manifold Leak Decay → SOC Balancing & Pre-Charge → Utility Storage Containers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Module Glycol Tray Bond | 1,224 s | 25 min | 95% | 99.1% | 30 | 51 (1.70 d) | 40 |
| 2. 314Ah Cell Laser Strapping | 1,404 s | 20 min | 93% | 98.4% | 18 | 45 (1.50 d) | 34 |
| 3. Rack String BMS & Pyro Fuse | 1,944 s | 18 min | 86% | 95.8% | 12 | 60 (2.00 d) | 22 |
| 4. Glycol Manifold Leak Decay | 1,440 s | 12 min | 93% | 97.6% | 8 | 33 (1.10 d) | 32 |
| 5. SOC Balancing & Pre-Charge | 1,152 s | 10 min | 96% | 99.0% | 6 | 24 (0.80 d) | 42 |
Key figures
- Takt time
- 1,800 s
- Lead time
- 8.63 d
- Value-added time
- 7,164 s
- Process cycle efficiency (PCE)
- 1.5%
- Rolled throughput yield (RTY)
- 90.3%
- Customer demand per day
- 30 units
- Line capacity per day
- 22 units
- Bottleneck
- Rack String BMS & Pyro Fuse
Reading the bottleneck
The bottleneck is "Rack String BMS & Pyro Fuse": it can process 22 units per day against a demand of 30 units, so it falls short of demand by 27.5%. Once downtime and scrap are counted, its cycle time grows from 1,944 s to 2,360 s, against a takt of 1,800 s. The largest loss at this step is equipment downtime (uptime 86%), about 316 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Switchgear, UPS & Power Systems: Switchgear, UPS & Power Systems
- 24kV SF6-Free Gas-Insulated Switchgear Bay
- Withdrawable 4000A Low-Voltage MCC Lineup
- 2.5MVA Cast-Resin Dry Distribution Transformer
- 350kW Liquid-Cooled EV Highway Fast Charger
- Modular 1MW Online Double-Conversion UPS
- Intelligent 42-Breaker Monitored Rack PDU
- 1500V Utility 250kW String Solar Inverter
- IEC-61850 Digital Substation Protection Relay
- 4000A Solenoid-Operated Automatic Transfer Switch
- Active Harmonic Filter & Capacitor Bank
- Multi-Axis EtherCAT Industrial Servo Drive