400kWh Grid Liquid-Cooled LFP Battery Rack

Product family: UL-9540A BESS Modules.

Flow: 314Ah LFP Cell Plants → Module Glycol Tray Bond → 314Ah Cell Laser Strapping → Rack String BMS & Pyro Fuse → Glycol Manifold Leak Decay → SOC Balancing & Pre-Charge → Utility Storage Containers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 400kWh Grid Liquid-Cooled LFP Battery RackSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. 314Ah LFP Cell Plants → Module Glycol Tray Bond (1,224 s) → 314Ah Cell Laser Strapping (1,404 s) → Rack String BMS & Pyro Fuse (1,944 s) → Glycol Manifold Leak Decay (1,440 s) → SOC Balancing & Pre-Charge (1,152 s) → Utility Storage Containers.SUPPLIER314Ah LFP CellPlantsI1.70 d1Module GlycolTray BondC/T 1,224 sI1.50 d2314Ah Cell LaserStrappingC/T 1,404 sI2.00 d3Rack String BMS &Pyro FuseC/T 1,944 sI1.10 d4Glycol ManifoldLeak DecayC/T 1,440 sI0.80 d5SOC Balancing &Pre-ChargeC/T 1,152 sI1.40 dCUSTOMERUtility StorageContainers30 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Module Glycol Tray Bond1,224 s25 min95%99.1%3051 (1.70 d)40
2. 314Ah Cell Laser Strapping1,404 s20 min93%98.4%1845 (1.50 d)34
3. Rack String BMS & Pyro Fuse1,944 s18 min86%95.8%1260 (2.00 d)22
4. Glycol Manifold Leak Decay1,440 s12 min93%97.6%833 (1.10 d)32
5. SOC Balancing & Pre-Charge1,152 s10 min96%99.0%624 (0.80 d)42

Key figures

Takt time
1,800 s
Lead time
8.63 d
Value-added time
7,164 s
Process cycle efficiency (PCE)
1.5%
Rolled throughput yield (RTY)
90.3%
Customer demand per day
30 units
Line capacity per day
22 units
Bottleneck
Rack String BMS & Pyro Fuse

Reading the bottleneck

The bottleneck is "Rack String BMS & Pyro Fuse": it can process 22 units per day against a demand of 30 units, so it falls short of demand by 27.5%. Once downtime and scrap are counted, its cycle time grows from 1,944 s to 2,360 s, against a takt of 1,800 s. The largest loss at this step is equipment downtime (uptime 86%), about 316 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.