24kV SF6-Free Gas-Insulated Switchgear Bay

Product family: Dry-Air Vacuum MV Cubicles.

Flow: Vacuum Interrupter OEMs → Laser Tight SS Tank Seam Weld → Vacuum Bottle & Drive Gear Fit → Helium Mass-Spec Leak Test → Clean Air 1.4-Bar Pressure Fill → 125kV BIL Impulse & PD Lab → Substation & Wind Integrators

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 24kV SF6-Free Gas-Insulated Switchgear BaySupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Vacuum Interrupter OEMs → Laser Tight SS Tank Seam Weld (1,669 s) → Vacuum Bottle & Drive Gear Fit (1,915 s) → Helium Mass-Spec Leak Test (2,651 s) → Clean Air 1.4-Bar Pressure Fill (1,964 s) → 125kV BIL Impulse & PD Lab (1,571 s) → Substation & Wind Integrators.SUPPLIERVacuumInterrupterOEMsI1.68 d1Laser Tight SSTank Seam WeldC/T 1,669 sI1.50 d2Vacuum Bottle &Drive Gear FitC/T 1,915 sI2.00 d3Helium Mass-SpecLeak TestC/T 2,651 sI1.09 d4Clean Air 1.4-BarPressure FillC/T 1,964 sI0.82 d5125kV BIL Impulse& PD LabC/T 1,571 sI1.41 dCUSTOMERSubstation &Wind…22 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Laser Tight SS Tank Seam Weld1,669 s25 min95%99.1%2237 (1.68 d)30
2. Vacuum Bottle & Drive Gear Fit1,915 s20 min93%98.4%1333 (1.50 d)25
3. Helium Mass-Spec Leak Test2,651 s18 min86%95.8%944 (2.00 d)16
4. Clean Air 1.4-Bar Pressure Fill1,964 s12 min93%97.6%624 (1.09 d)24
5. 125kV BIL Impulse & PD Lab1,571 s10 min96%99.0%418 (0.82 d)31

Key figures

Takt time
2,455 s
Lead time
8.68 d
Value-added time
9,770 s
Process cycle efficiency (PCE)
2.1%
Rolled throughput yield (RTY)
90.3%
Customer demand per day
22 units
Line capacity per day
16 units
Bottleneck
Helium Mass-Spec Leak Test

Reading the bottleneck

The bottleneck is "Helium Mass-Spec Leak Test": it can process 16 units per day against a demand of 22 units, so it falls short of demand by 27.4%. Once downtime and scrap are counted, its cycle time grows from 2,651 s to 3,218 s, against a takt of 2,455 s. The largest loss at this step is equipment downtime (uptime 86%), about 432 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.