33kV Underground Distribution AL/XLPE Cable

Product family: Triplexed Utility Feeder Cables.

Flow: Aluminum E-Rod Supplier → 7-Wire Waterblock Strand → CCV Peroxide XLPE Cure Line → Copper Wire Concentric Screen → HDPE Red Termite Sheathing → Partial Discharge Tank Test → Grid Distribution DSOs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 33kV Underground Distribution AL/XLPE CableSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Aluminum E-Rod Supplier → 7-Wire Waterblock Strand (1,224 s) → CCV Peroxide XLPE Cure Line (1,476 s) → Copper Wire Concentric Screen (1,926 s) → HDPE Red Termite Sheathing (1,404 s) → Partial Discharge Tank Test (1,080 s) → Grid Distribution DSOs.SUPPLIERAluminum E-RodSupplierI1.60 d17-Wire WaterblockStrandC/T 1,224 sI1.80 d2CCV Peroxide XLPECure LineC/T 1,476 sI2.40 d3Copper WireConcentric ScreenC/T 1,926 sI1.40 d4HDPE Red TermiteSheathingC/T 1,404 sI0.91 d5Partial DischargeTank TestC/T 1,080 sI1.80 dCUSTOMERGridDistribution…45 / batches

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 7-Wire Waterblock Strand1,224 s35 min94%99.2%6872 (1.60 d)61
2. CCV Peroxide XLPE Cure Line1,476 s50 min91%98.5%6881 (1.80 d)48
3. Copper Wire Concentric Screen1,926 s95 min83%96.4%90108 (2.40 d)32
4. HDPE Red Termite Sheathing1,404 s30 min93%98.7%4563 (1.40 d)52
5. Partial Discharge Tank Test1,080 s12 min97%99.3%2341 (0.91 d)71

Key figures

Takt time
1,800 s
Lead time
10.00 d
Value-added time
7,110 s
Process cycle efficiency (PCE)
0.88%
Rolled throughput yield (RTY)
92.3%
Customer demand per day
45 batches
Line capacity per day
32 batches
Bottleneck
Copper Wire Concentric Screen

Reading the bottleneck

The bottleneck is "Copper Wire Concentric Screen": it can process 32 batches per day against a demand of 45 batches, so it falls short of demand by 27.9%. Once downtime and scrap are counted, its cycle time grows from 1,926 s to 2,407 s, against a takt of 1,800 s. The largest loss at this step is equipment downtime (uptime 83%), about 394 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.