1500V EN-50618 Cross-Linked Solar Cable

Product family: E-Beam Cured PV Twin Cable.

Flow: Tinned Electrolytic Cu → Fine-Wire Tinning & Bunch → Dual-Layer Color Extrusion → 10MeV Electron-Beam Crosslink → Spark Test 10kV Non-Stop → UV-Weathering Lot Coil Pack → Utility Solar String Arrays

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 1500V EN-50618 Cross-Linked Solar CableSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Tinned Electrolytic Cu → Fine-Wire Tinning & Bunch (459 s) → Dual-Layer Color Extrusion (554 s) → 10MeV Electron-Beam Crosslink (722 s) → Spark Test 10kV Non-Stop (527 s) → UV-Weathering Lot Coil Pack (405 s) → Utility Solar String Arrays.SUPPLIERTinnedElectrolytic CuI1.60 d1Fine-Wire Tinning& BunchC/T 459 sI1.80 d2Dual-Layer ColorExtrusionC/T 554 sI2.40 d310MeVElectron-Beam…C/T 722 sI1.40 d4Spark Test 10kVNon-StopC/T 527 sI0.90 d5UV-Weathering LotCoil PackC/T 405 sI1.80 dCUSTOMERUtility SolarString Arrays120 / batches

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Fine-Wire Tinning & Bunch459 s35 min94%99.2%180192 (1.60 d)162
2. Dual-Layer Color Extrusion554 s50 min91%98.5%180216 (1.80 d)128
3. 10MeV Electron-Beam Crosslink722 s95 min83%96.4%240288 (2.40 d)87
4. Spark Test 10kV Non-Stop527 s30 min93%98.7%120168 (1.40 d)138
5. UV-Weathering Lot Coil Pack405 s12 min97%99.3%60108 (0.90 d)189

Key figures

Takt time
675 s
Lead time
9.93 d
Value-added time
2,667 s
Process cycle efficiency (PCE)
0.33%
Rolled throughput yield (RTY)
92.3%
Customer demand per day
120 batches
Line capacity per day
87 batches
Bottleneck
10MeV Electron-Beam Crosslink

Reading the bottleneck

The bottleneck is "10MeV Electron-Beam Crosslink": it can process 87 batches per day against a demand of 120 batches, so it falls short of demand by 27.8%. Once downtime and scrap are counted, its cycle time grows from 722 s to 902 s, against a takt of 675 s. The largest loss at this step is equipment downtime (uptime 83%), about 148 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.