Automated ICE/BEV Cockpit Wire Harness

Product family: 600-Circuit Zone Harnesses.

Flow: Automotive Terminal Suppliers → Auto Cut-Strip-Crimp → Ultrasonic Splice Junctions → Rotary Conveyor Formboard Build → Clip, Conduit & Felt Wrap → Vision Fuse & Pushback Pin QC → Vehicle Assembly Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Automated ICE/BEV Cockpit Wire HarnessSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Automotive Terminal Suppliers → Auto Cut-Strip-Crimp (39.9 s) → Ultrasonic Splice Junctions (48.0 s) → Rotary Conveyor Formboard Build (63.0 s) → Clip, Conduit & Felt Wrap (46.0 s) → Vision Fuse & Pushback Pin QC (35.2 s) → Vehicle Assembly Line.SUPPLIERAutomotiveTerminalSuppliersI1.60 d1AutoCut-Strip-CrimpC/T 39.9 sI1.80 d2Ultrasonic SpliceJunctionsC/T 48.0 sI2.40 d3Rotary ConveyorFormboard BuildC/T 63.0 sI1.40 d4Clip, Conduit &Felt WrapC/T 46.0 sI0.90 d5Vision Fuse &Pushback Pin QCC/T 35.2 sI1.80 dCUSTOMERVehicleAssembly Line920 / assemblies

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Auto Cut-Strip-Crimp39.9 s35 min94%99.2%1,3801,472 (1.60 d)1,229
2. Ultrasonic Splice Junctions48.0 s50 min91%98.5%1,3801,656 (1.80 d)971
3. Rotary Conveyor Formboard Build63.0 s95 min83%96.4%1,8402,208 (2.40 d)650
4. Clip, Conduit & Felt Wrap46.0 s30 min93%98.7%9201,288 (1.40 d)1,042
5. Vision Fuse & Pushback Pin QC35.2 s12 min97%99.3%460828 (0.90 d)1,438

Key figures

Takt time
58.7 s
Lead time
9.90 d
Value-added time
232 s
Process cycle efficiency (PCE)
0.043%
Rolled throughput yield (RTY)
92.3%
Customer demand per day
920 assemblies
Line capacity per day
650 assemblies
Bottleneck
Rotary Conveyor Formboard Build

Reading the bottleneck

The bottleneck is "Rotary Conveyor Formboard Build": it can process 650 assemblies per day against a demand of 920 assemblies, so it falls short of demand by 29.4%. Once downtime and scrap are counted, its cycle time grows from 63.0 s to 78.7 s, against a takt of 58.7 s. The largest loss at this step is equipment downtime (uptime 83%), about 12.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.