120MW Francis Hydro Turbine Runner Overhaul

Product family: Cavitation Laser-Clad Restore.

Flow: Cobalt-Alloy Wire & Martensitic → NDT Crack Map & Gouge Prep → Robotic Cobalt-Alloy Cavitation Clad → 5-Axis Blade Profile Finish → Stress-Relief & Phased UT → Dynamic Balancing & Shaft Rig → Alpine Pumped-Storage Dams

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 120MW Francis Hydro Turbine Runner OverhaulSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Cobalt-Alloy Wire & Martensitic → NDT Crack Map & Gouge Prep (8,775 s) → Robotic Cobalt-Alloy Cavitation Clad (10,800 s) → 5-Axis Blade Profile Finish (14,445 s) → Stress-Relief & Phased UT (9,990 s) → Dynamic Balancing & Shaft Rig (7,020 s) → Alpine Pumped-Storage Dams.SUPPLIERCobalt-AlloyWire &MartensiticI1.50 d1NDT Crack Map &Gouge PrepC/T 8,775 sI1.50 d2RoboticCobalt-Alloy…C/T 10,800 sI2.00 d35-Axis BladeProfile FinishC/T 14,445 sI1.00 d4Stress-Relief &Phased UTC/T 9,990 sI0.50 d5Dynamic Balancing& Shaft RigC/T 7,020 sI1.00 dCUSTOMERAlpinePumped-Storage…2 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. NDT Crack Map & Gouge Prep8,775 s20 min94%98.5%23 (1.50 d)3
2. Robotic Cobalt-Alloy Cavitation Clad10,800 s25 min91%96.4%23 (1.50 d)2
3. 5-Axis Blade Profile Finish14,445 s45 min85%92.0%14 (2.00 d)1
4. Stress-Relief & Phased UT9,990 s15 min95%97.5%12 (1.00 d)2
5. Dynamic Balancing & Shaft Rig7,020 s8 min97%99.1%11 (0.50 d)4

Key figures

Takt time
13,500 s
Lead time
9.39 d
Value-added time
51,030 s
Process cycle efficiency (PCE)
20.1%
Rolled throughput yield (RTY)
84.4%
Customer demand per day
2 units
Line capacity per day
1 units
Bottleneck
5-Axis Blade Profile Finish

Reading the bottleneck

The bottleneck is "5-Axis Blade Profile Finish": it can process 1 units per day against a demand of 2 units, so it falls short of demand by 30.6%. Once downtime and scrap are counted, its cycle time grows from 14,445 s to 18,472 s, against a takt of 13,500 s. The largest loss at this step is changeovers (45 min every 1 units), about 2,700 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.