Utility Solar PV Skid & Grid Commissioning
Product family: 2.5 MW Solar Inverter Skids.
Flow: PV Tier-1 & Transformer OEM → Structure Kitting → DC Array Wiring → HV Inverter Commissioning → SCADA Grid Sync → Utility Energize Sign → Utility Grid Operators
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Structure Kitting | 1,170 s | 20 min | 94% | 98.5% | 15 | 24 (1.60 d) | 20 |
| 2. DC Array Wiring | 1,440 s | 25 min | 91% | 96.4% | 12 | 23 (1.53 d) | 15 |
| 3. HV Inverter Commissioning | 1,926 s | 45 min | 85% | 92.0% | 9 | 33 (2.20 d) | 9 |
| 4. SCADA Grid Sync | 1,332 s | 15 min | 95% | 97.5% | 6 | 15 (1.00 d) | 17 |
| 5. Utility Energize Sign | 936 s | 8 min | 97% | 99.1% | 3 | 9 (0.60 d) | 25 |
Key figures
- Takt time
- 1,800 s
- Lead time
- 7.99 d
- Value-added time
- 6,804 s
- Process cycle efficiency (PCE)
- 3.2%
- Rolled throughput yield (RTY)
- 84.4%
- Customer demand per day
- 15 skids
- Line capacity per day
- 9 skids
- Bottleneck
- HV Inverter Commissioning
Reading the bottleneck
The bottleneck is "HV Inverter Commissioning": it can process 9 skids per day against a demand of 15 skids, so it falls short of demand by 39.1%. Once downtime and scrap are counted, its cycle time grows from 1,926 s to 2,463 s, against a takt of 1,800 s. The largest loss at this step is equipment downtime (uptime 85%), about 340 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Solar PV, Wind, Hydrogen & BESS: Solar PV, Wind, Hydrogen & BESS
- 15MW Offshore Wind Turbine Nacelle Assembly
- 20MW PEM Green Hydrogen Electrolyzer Container
- 4MWh 20ft Utility BESS Battery Storage Container
- Biomethane RNG Anaerobic Digester & Membrane
- Offshore Rope-Access Wind Blade Leading-Edge Fix
- Parabolic Concentrated Solar Thermal Facet Mirror
- 120MW Francis Hydro Turbine Runner Overhaul
- Geothermal Binary Organic Rankine Cycle Plant
- HDPE Modular Floating Solar Reservoir Array
- Dual-Pillar Cantilever Commercial EV Solar Carport
- Factory SMR Nuclear Heat Exchanger Coil Module