Utility Solar PV Skid & Grid Commissioning

Product family: 2.5 MW Solar Inverter Skids.

Flow: PV Tier-1 & Transformer OEM → Structure Kitting → DC Array Wiring → HV Inverter Commissioning → SCADA Grid Sync → Utility Energize Sign → Utility Grid Operators

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Utility Solar PV Skid & Grid CommissioningSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. PV Tier-1 & Transformer OEM → Structure Kitting (1,170 s) → DC Array Wiring (1,440 s) → HV Inverter Commissioning (1,926 s) → SCADA Grid Sync (1,332 s) → Utility Energize Sign (936 s) → Utility Grid Operators.SUPPLIERPV Tier-1 &Transformer OEMI1.60 d1Structure KittingC/T 1,170 sI1.53 d2DC Array WiringC/T 1,440 sI2.20 d3HV InverterCommissioningC/T 1,926 sI1.00 d4SCADA Grid SyncC/T 1,332 sI0.60 d5Utility EnergizeSignC/T 936 sI0.80 dCUSTOMERUtility GridOperators15 / skids

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Structure Kitting1,170 s20 min94%98.5%1524 (1.60 d)20
2. DC Array Wiring1,440 s25 min91%96.4%1223 (1.53 d)15
3. HV Inverter Commissioning1,926 s45 min85%92.0%933 (2.20 d)9
4. SCADA Grid Sync1,332 s15 min95%97.5%615 (1.00 d)17
5. Utility Energize Sign936 s8 min97%99.1%39 (0.60 d)25

Key figures

Takt time
1,800 s
Lead time
7.99 d
Value-added time
6,804 s
Process cycle efficiency (PCE)
3.2%
Rolled throughput yield (RTY)
84.4%
Customer demand per day
15 skids
Line capacity per day
9 skids
Bottleneck
HV Inverter Commissioning

Reading the bottleneck

The bottleneck is "HV Inverter Commissioning": it can process 9 skids per day against a demand of 15 skids, so it falls short of demand by 39.1%. Once downtime and scrap are counted, its cycle time grows from 1,926 s to 2,463 s, against a takt of 1,800 s. The largest loss at this step is equipment downtime (uptime 85%), about 340 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Solar PV, Wind, Hydrogen & BESS: Solar PV, Wind, Hydrogen & BESS