15,000-Bun/Hr QSR Brioche Hamburger Bun Line

Product family: Pre-Sliced Toasted Crown Buns.

Flow: Liquid Egg & High-Prot Flour → High-Speed Sponge Mix → 6-Across Pan Divide & Proofer → Egg-Wash Spray & Gas Bake → Vacuum Depan & Twin Slicer → Tray Crate Stack & Frozen Dock → Quick-Service Restaurant Hubs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 15,000-Bun/Hr QSR Brioche Hamburger Bun LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Liquid Egg & High-Prot Flour → High-Speed Sponge Mix (1.3 s) → 6-Across Pan Divide & Proofer (1.6 s) → Egg-Wash Spray & Gas Bake (2.0 s) → Vacuum Depan & Twin Slicer (1.5 s) → Tray Crate Stack & Frozen Dock (1.2 s) → Quick-Service Restaurant Hubs.SUPPLIERLiquid Egg &High-Prot FlourI0.90 d1High-Speed SpongeMixC/T 1.3 sI1.00 d26-Across PanDivide & ProoferC/T 1.6 sI1.30 d3Egg-Wash Spray &Gas BakeC/T 2.0 sI0.80 d4Vacuum Depan &Twin SlicerC/T 1.5 sI0.70 d5Tray Crate Stack& Frozen DockC/T 1.2 sI1.20 dCUSTOMERQuick-ServiceRestaurant Hubs42,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. High-Speed Sponge Mix1.3 s25 min95%99.0%25,20037,800 (0.90 d)56,792
2. 6-Across Pan Divide & Proofer1.6 s30 min92%98.1%21,00042,000 (1.00 d)43,659
3. Egg-Wash Spray & Gas Bake2.0 s45 min85%96.4%33,60054,600 (1.30 d)31,803
4. Vacuum Depan & Twin Slicer1.5 s12 min94%98.6%12,60033,600 (0.80 d)48,566
5. Tray Crate Stack & Frozen Dock1.2 s18 min93%99.2%12,60029,400 (0.70 d)59,505

Key figures

Takt time
1.9 s
Lead time
5.90 d
Value-added time
7.6 s
Process cycle efficiency (PCE)
0.002%
Rolled throughput yield (RTY)
91.6%
Customer demand per day
42,000 packs
Line capacity per day
31,803 packs
Bottleneck
Egg-Wash Spray & Gas Bake

Reading the bottleneck

The bottleneck is "Egg-Wash Spray & Gas Bake": it can process 31,803 packs per day against a demand of 42,000 packs, so it falls short of demand by 24.3%. Once downtime and scrap are counted, its cycle time grows from 2.0 s to 2.4 s, against a takt of 1.9 s. The largest loss at this step is equipment downtime (uptime 85%), about 0.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.