Automated 8,000-Loaf/Hr Pan Bread Bakery Line

Product family: 750g Sliced Wholegrain Loaves.

Flow: Regional Flour Mills → Sponge-Dough Bulk Ferment → 4-Pocket Divider & Tin Drop → Tunnel Gas Hearth Bake → 2-Hr Spiral Depan Cooler → Band Slicer & Twist-Tie Bag → Daily Supermarket Routes

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Automated 8,000-Loaf/Hr Pan Bread Bakery LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Regional Flour Mills → Sponge-Dough Bulk Ferment (1.7 s) → 4-Pocket Divider & Tin Drop (2.1 s) → Tunnel Gas Hearth Bake (2.7 s) → 2-Hr Spiral Depan Cooler (2.0 s) → Band Slicer & Twist-Tie Bag (1.6 s) → Daily Supermarket Routes.SUPPLIERRegional FlourMillsI0.90 d1Sponge-Dough BulkFermentC/T 1.7 sI1.00 d24-Pocket Divider& Tin DropC/T 2.1 sI1.30 d3Tunnel Gas HearthBakeC/T 2.7 sI0.80 d42-Hr Spiral DepanCoolerC/T 2.0 sI0.70 d5Band Slicer &Twist-Tie BagC/T 1.6 sI1.20 dCUSTOMERDailySupermarket…32,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Sponge-Dough Bulk Ferment1.7 s25 min95%99.0%19,20028,800 (0.90 d)43,429
2. 4-Pocket Divider & Tin Drop2.1 s30 min92%98.1%16,00032,000 (1.00 d)33,264
3. Tunnel Gas Hearth Bake2.7 s45 min85%96.4%25,60041,600 (1.30 d)23,558
4. 2-Hr Spiral Depan Cooler2.0 s12 min94%98.6%9,60025,600 (0.80 d)36,425
5. Band Slicer & Twist-Tie Bag1.6 s18 min93%99.2%9,60022,400 (0.70 d)44,629

Key figures

Takt time
2.5 s
Lead time
5.90 d
Value-added time
10.1 s
Process cycle efficiency (PCE)
0.002%
Rolled throughput yield (RTY)
91.6%
Customer demand per day
32,000 packs
Line capacity per day
23,558 packs
Bottleneck
Tunnel Gas Hearth Bake

Reading the bottleneck

The bottleneck is "Tunnel Gas Hearth Bake": it can process 23,558 packs per day against a demand of 32,000 packs, so it falls short of demand by 26.4%. Once downtime and scrap are counted, its cycle time grows from 2.7 s to 3.3 s, against a takt of 2.5 s. The largest loss at this step is equipment downtime (uptime 85%), about 0.5 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.