Conched Bean-to-Bar Tempered Chocolate Line

Product family: 100g Single-Origin Tablets.

Flow: West Africa Cocoa Mass → 5-Roll Refiner & 24h Conche → 3-Zone Precision Temper → Polycarbonate Mold Fill & Vibe → 14m Glycol Cooling Demold → Foil Wrap & Paper Sleeve → Global Confectionery

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Conched Bean-to-Bar Tempered Chocolate LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. West Africa Cocoa Mass → 5-Roll Refiner & 24h Conche (1.3 s) → 3-Zone Precision Temper (1.6 s) → Polycarbonate Mold Fill & Vibe (2.0 s) → 14m Glycol Cooling Demold (1.5 s) → Foil Wrap & Paper Sleeve (1.2 s) → Global Confectionery.SUPPLIERWest AfricaCocoa MassI0.90 d15-Roll Refiner &24h ConcheC/T 1.3 sI1.00 d23-Zone PrecisionTemperC/T 1.6 sI1.30 d3PolycarbonateMold Fill & VibeC/T 2.0 sI0.80 d414m GlycolCooling DemoldC/T 1.5 sI0.70 d5Foil Wrap & PaperSleeveC/T 1.2 sI1.20 dCUSTOMERGlobalConfectionery28,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 5-Roll Refiner & 24h Conche1.3 s25 min95%99.0%16,80025,200 (0.90 d)37,258
2. 3-Zone Precision Temper1.6 s30 min92%98.1%14,00028,000 (1.00 d)28,429
3. Polycarbonate Mold Fill & Vibe2.0 s45 min85%96.4%22,40036,400 (1.30 d)20,741
4. 14m Glycol Cooling Demold1.5 s12 min94%98.6%8,40022,400 (0.80 d)31,883
5. Foil Wrap & Paper Sleeve1.2 s18 min93%99.2%8,40019,600 (0.70 d)38,748

Key figures

Takt time
1.9 s
Lead time
5.90 d
Value-added time
7.6 s
Process cycle efficiency (PCE)
0.002%
Rolled throughput yield (RTY)
91.6%
Customer demand per day
28,000 packs
Line capacity per day
20,741 packs
Bottleneck
Polycarbonate Mold Fill & Vibe

Reading the bottleneck

The bottleneck is "Polycarbonate Mold Fill & Vibe": it can process 20,741 packs per day against a demand of 28,000 packs, so it falls short of demand by 25.9%. Once downtime and scrap are counted, its cycle time grows from 2.0 s to 2.4 s, against a takt of 1.9 s. The largest loss at this step is equipment downtime (uptime 85%), about 0.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Bakery, Biscuits & Confectionery: Bakery, Biscuits & Confectionery