60mL Functional Energy & Vitamin Shot Line

Product family: High-Speed Shot Sleeving.

Flow: B-Vitamin Concentrates → Small-Batch Micro-Formulation → 24-Head Rotary Micro-Filler → Tamper Band & Foil Induction → Tray Erect & Shrink 12-Shot → Case Load & Expiration Check → Convenience Checkout Display

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 60mL Functional Energy & Vitamin Shot LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. B-Vitamin Concentrates → Small-Batch Micro-Formulation (2.0 s) → 24-Head Rotary Micro-Filler (3.1 s) → Tamper Band & Foil Induction (2.3 s) → Tray Erect & Shrink 12-Shot (2.4 s) → Case Load & Expiration Check (1.9 s) → Convenience Checkout Display.SUPPLIERB-VitaminConcentratesI1.80 d1Small-BatchMicro-FormulationC/T 2.0 sI1.50 d224-Head RotaryMicro-FillerC/T 3.1 sI1.40 d3Tamper Band &Foil InductionC/T 2.3 sI1.20 d4Tray Erect &Shrink 12-ShotC/T 2.4 sI0.80 d5Case Load &Expiration CheckC/T 1.9 sI1.50 dCUSTOMERConvenienceCheckout…18,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Small-Batch Micro-Formulation2.0 s45 min92%98.8%21,60032,400 (1.80 d)23,519
2. 24-Head Rotary Micro-Filler3.1 s65 min84%96.8%21,60027,000 (1.50 d)13,312
3. Tamper Band & Foil Induction2.3 s25 min92%98.2%10,80025,200 (1.40 d)20,229
4. Tray Erect & Shrink 12-Shot2.4 s30 min91%98.5%9,00021,600 (1.20 d)18,823
5. Case Load & Expiration Check1.9 s10 min96%99.5%5,40014,400 (0.80 d)26,142

Key figures

Takt time
3.0 s
Lead time
8.20 d
Value-added time
11.7 s
Process cycle efficiency (PCE)
0.003%
Rolled throughput yield (RTY)
92.0%
Customer demand per day
18,000 packs
Line capacity per day
13,312 packs
Bottleneck
24-Head Rotary Micro-Filler

Reading the bottleneck

The bottleneck is "24-Head Rotary Micro-Filler": it can process 13,312 packs per day against a demand of 18,000 packs, so it falls short of demand by 26.0%. Once downtime and scrap are counted, its cycle time grows from 3.1 s to 3.8 s, against a takt of 3.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.6 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.