45,000 cph Aluminum Craft Beer Canning Line

Product family: 330mL Sleek Beer Cans.

Flow: Aluminum Can Supplier → Cold Bright Tank Carb → Rotary N2 Purge & Seam → Tunnel Flash Pasteurize → Rotary Neck Sleeve & Date → Tray Pak & Robot Pallet → Supermarkets & Hospitality

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 45,000 cph Aluminum Craft Beer Canning LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Aluminum Can Supplier → Cold Bright Tank Carb (2.6 s) → Rotary N2 Purge & Seam (4.0 s) → Tunnel Flash Pasteurize (2.9 s) → Rotary Neck Sleeve & Date (3.1 s) → Tray Pak & Robot Pallet (2.5 s) → Supermarkets & Hospitality.SUPPLIERAluminum CanSupplierI1.80 d1Cold Bright TankCarbC/T 2.6 sI1.50 d2Rotary N2 Purge &SeamC/T 4.0 sI1.40 d3Tunnel FlashPasteurizeC/T 2.9 sI1.20 d4Rotary NeckSleeve & DateC/T 3.1 sI0.80 d5Tray Pak & RobotPalletC/T 2.5 sI1.50 dCUSTOMERSupermarkets &Hospitality14,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Cold Bright Tank Carb2.6 s45 min92%98.8%16,80025,200 (1.80 d)18,092
2. Rotary N2 Purge & Seam4.0 s65 min84%96.8%16,80021,000 (1.50 d)10,316
3. Tunnel Flash Pasteurize2.9 s25 min92%98.2%8,40019,600 (1.40 d)16,044
4. Rotary Neck Sleeve & Date3.1 s30 min91%98.5%7,00016,800 (1.20 d)14,573
5. Tray Pak & Robot Pallet2.5 s10 min96%99.5%4,20011,200 (0.80 d)19,868

Key figures

Takt time
3.9 s
Lead time
8.20 d
Value-added time
15.1 s
Process cycle efficiency (PCE)
0.003%
Rolled throughput yield (RTY)
92.0%
Customer demand per day
14,000 packs
Line capacity per day
10,316 packs
Bottleneck
Rotary N2 Purge & Seam

Reading the bottleneck

The bottleneck is "Rotary N2 Purge & Seam": it can process 10,316 packs per day against a demand of 14,000 packs, so it falls short of demand by 26.3%. Once downtime and scrap are counted, its cycle time grows from 4.0 s to 4.9 s, against a takt of 3.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.