High-Value Distilled Spirits Tax-Stamp Line

Product family: 700mL Glass Spirits & Tax Seal.

Flow: Luxury Glass Bottle Supplier → Chill Filtration & Proof Adjust → Level-Sense Gravity Filler → T-Bar Cork & Neck Tamper Foil → Excise Tax Stamp & Hologram → Magnetic Gift Carton & Case → Global Duty-Free & Spirits

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: High-Value Distilled Spirits Tax-Stamp LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Luxury Glass Bottle Supplier → Chill Filtration & Proof Adjust (10.2 s) → Level-Sense Gravity Filler (15.6 s) → T-Bar Cork & Neck Tamper Foil (11.4 s) → Excise Tax Stamp & Hologram (12.0 s) → Magnetic Gift Carton & Case (9.6 s) → Global Duty-Free & Spirits.SUPPLIERLuxury GlassBottle SupplierI1.80 d1Chill Filtration& Proof AdjustC/T 10.2 sI1.50 d2Level-SenseGravity FillerC/T 15.6 sI1.40 d3T-Bar Cork & NeckTamper FoilC/T 11.4 sI1.20 d4Excise Tax Stamp& HologramC/T 12.0 sI0.80 d5Magnetic GiftCarton & CaseC/T 9.6 sI1.50 dCUSTOMERGlobalDuty-Free &…3,600 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Chill Filtration & Proof Adjust10.2 s45 min92%98.8%4,3206,480 (1.80 d)4,612
2. Level-Sense Gravity Filler15.6 s65 min84%96.8%4,3205,400 (1.50 d)2,645
3. T-Bar Cork & Neck Tamper Foil11.4 s25 min92%98.2%2,1605,040 (1.40 d)4,081
4. Excise Tax Stamp & Hologram12.0 s30 min91%98.5%1,8004,320 (1.20 d)3,765
5. Magnetic Gift Carton & Case9.6 s10 min96%99.5%1,0802,880 (0.80 d)5,174

Key figures

Takt time
15.0 s
Lead time
8.20 d
Value-added time
58.8 s
Process cycle efficiency (PCE)
0.013%
Rolled throughput yield (RTY)
92.0%
Customer demand per day
3,600 packs
Line capacity per day
2,645 packs
Bottleneck
Level-Sense Gravity Filler

Reading the bottleneck

The bottleneck is "Level-Sense Gravity Filler": it can process 2,645 packs per day against a demand of 3,600 packs, so it falls short of demand by 26.5%. Once downtime and scrap are counted, its cycle time grows from 15.6 s to 19.2 s, against a takt of 15.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 3.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.