12,000 bph Winery Bottling, Cork & Capsule
Product family: 750mL Bordeaux Glass Bottles.
Flow: Cork Stopper & Glass Bottle Suppliers → Cross-Flow Membrane Polish → Vacuum Inert Filler & Corker → Heat-Shrink PVC/Tin Capsule → Front/Back/Medal Precision Lab → Partitioned 6-Bottle Case Pack → Domestic & Export Wine Trade
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Cross-Flow Membrane Polish | 4.4 s | 45 min | 92% | 98.8% | 5,040 | 7,560 (1.80 d) | 5,113 |
| 2. Vacuum Inert Filler & Corker | 6.7 s | 65 min | 84% | 96.8% | 5,040 | 6,300 (1.50 d) | 2,882 |
| 3. Heat-Shrink PVC/Tin Capsule | 4.9 s | 25 min | 92% | 98.2% | 2,520 | 5,880 (1.40 d) | 4,517 |
| 4. Front/Back/Medal Precision Lab | 5.1 s | 30 min | 91% | 98.5% | 2,100 | 5,040 (1.20 d) | 4,113 |
| 5. Partitioned 6-Bottle Case Pack | 4.1 s | 10 min | 96% | 99.5% | 1,260 | 3,360 (0.80 d) | 5,824 |
Key figures
- Takt time
- 6.4 s
- Lead time
- 8.20 d
- Value-added time
- 25.2 s
- Process cycle efficiency (PCE)
- 0.011%
- Rolled throughput yield (RTY)
- 92.0%
- Customer demand per day
- 4,200 packs
- Line capacity per day
- 2,882 packs
- Bottleneck
- Vacuum Inert Filler & Corker
Reading the bottleneck
The bottleneck is "Vacuum Inert Filler & Corker": it can process 2,882 packs per day against a demand of 4,200 packs, so it falls short of demand by 31.4%. Once downtime and scrap are counted, its cycle time grows from 6.7 s to 8.2 s, against a takt of 6.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 1.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Bottling, Canning & Beverages: Bottling, Canning & Beverages
- 18,000 bph PET Bottling Line
- 45,000 cph Aluminum Craft Beer Canning Line
- 30,000 bph Returnable Glass Soda Line
- 8,000 bph 5L Spring Water PET Combi-Line
- High-Pressure Pasteurized (HPP) Cold Juice
- Hot-Fill / Aseptic Sport Isotonic Cap Line
- 60mL Functional Energy & Vitamin Shot Line
- Organic Glass Kombucha Secondary Ferment
- Retort Nitro Cold-Brew Aluminum Can Line
- Automated Stainless 30L Beer Keg Wash & Fill
- High-Value Distilled Spirits Tax-Stamp Line