30,000 bph Returnable Glass Soda Line

Product family: Reusable Crated Glass Bottles.

Flow: Glass Loop Crates → Crate Unpack & Caustic Wash → Empty Bottle Optical EBI → Isobaric Fill & Crown Cap → Wet-Glue Paper Label & Date → Auto Re-Crate & Palletize → HORECA & Retail Networks

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 30,000 bph Returnable Glass Soda LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Glass Loop Crates → Crate Unpack & Caustic Wash (6.7 s) → Empty Bottle Optical EBI (10.3 s) → Isobaric Fill & Crown Cap (7.5 s) → Wet-Glue Paper Label & Date (7.9 s) → Auto Re-Crate & Palletize (6.3 s) → HORECA & Retail Networks.SUPPLIERGlass LoopCratesI1.80 d1Crate Unpack &Caustic WashC/T 6.7 sI1.50 d2Empty BottleOptical EBIC/T 10.3 sI1.40 d3Isobaric Fill &Crown CapC/T 7.5 sI1.20 d4Wet-Glue PaperLabel & DateC/T 7.9 sI0.80 d5Auto Re-Crate &PalletizeC/T 6.3 sI1.50 dCUSTOMERHORECA & RetailNetworks8,200 / crates

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Crate Unpack & Caustic Wash6.7 s45 min92%98.8%9,84014,760 (1.80 d)10,684
2. Empty Bottle Optical EBI10.3 s65 min84%96.8%9,84012,300 (1.50 d)6,138
3. Isobaric Fill & Crown Cap7.5 s25 min92%98.2%4,92011,480 (1.40 d)9,456
4. Wet-Glue Paper Label & Date7.9 s30 min91%98.5%4,1009,840 (1.20 d)8,782
5. Auto Re-Crate & Palletize6.3 s10 min96%99.5%2,4606,560 (0.80 d)11,978

Key figures

Takt time
9.9 s
Lead time
8.20 d
Value-added time
38.7 s
Process cycle efficiency (PCE)
0.006%
Rolled throughput yield (RTY)
92.0%
Customer demand per day
8,200 crates
Line capacity per day
6,138 crates
Bottleneck
Empty Bottle Optical EBI

Reading the bottleneck

The bottleneck is "Empty Bottle Optical EBI": it can process 6,138 crates per day against a demand of 8,200 crates, so it falls short of demand by 25.1%. Once downtime and scrap are counted, its cycle time grows from 10.3 s to 12.7 s, against a takt of 9.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 2.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.