Enzymatic Oat Hydrolysis UHT Plant-Milk Line
Product family: Barista 1L Oat Drink Bricks.
Flow: Nordic Oat Flake Mills → Wet Milling & Enzyme Saccharif → Decanter Centrifuge Fiber Out → Oil Emulsion & UHT Steam Inj → Aseptic Brick Fill & Straw/Cap → Shrink 12-Pack Ambient Pallet → Cafes & Retail Channels
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Wet Milling & Enzyme Saccharif | 3.8 s | 25 min | 95% | 99.1% | 9,500 | 11,400 (1.20 d) | 13,007 |
| 2. Decanter Centrifuge Fiber Out | 4.5 s | 35 min | 92% | 98.4% | 7,600 | 10,450 (1.10 d) | 10,335 |
| 3. Oil Emulsion & UHT Steam Inj | 6.1 s | 85 min | 81% | 97.5% | 9,500 | 14,250 (1.50 d) | 6,331 |
| 4. Aseptic Brick Fill & Straw/Cap | 4.8 s | 30 min | 90% | 97.9% | 4,750 | 8,550 (0.90 d) | 9,252 |
| 5. Shrink 12-Pack Ambient Pallet | 3.5 s | 12 min | 96% | 99.4% | 3,800 | 10,450 (1.10 d) | 14,232 |
Key figures
- Takt time
- 5.7 s
- Lead time
- 7.20 d
- Value-added time
- 22.7 s
- Process cycle efficiency (PCE)
- 0.006%
- Rolled throughput yield (RTY)
- 92.5%
- Customer demand per day
- 9,500 packs
- Line capacity per day
- 6,331 packs
- Bottleneck
- Oil Emulsion & UHT Steam Inj
Reading the bottleneck
The bottleneck is "Oil Emulsion & UHT Steam Inj": it can process 6,331 packs per day against a demand of 9,500 packs, so it falls short of demand by 33.4%. Once downtime and scrap are counted, its cycle time grows from 6.1 s to 7.7 s, against a takt of 5.7 s. The largest loss at this step is equipment downtime (uptime 81%), about 1.4 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Dairy, UHT & Plant-Based Alt: Dairy, UHT & Plant-Based Alt
- UHT Aseptic Dairy Processing & Filling
- Ultrafiltered Stirred Greek Yogurt Cup Line
- Continuous Pasta-Filata Mozzarella Shred & Ball
- GMP Stage-1 Spray-Dried Infant Formula Can Line
- Rotary Extruded Chocolate-Dipped Ice Cream Bar
- Microfiltered Whey Isolate (WPI) Pouch & Tub Line
- Continuous Churn Cultured Butter Parchment Wrap
- Traditional Soft Surface-Ripened Cheese Flow
- Live 12-Strain Cultured Kefir PET Bottle
- Vacuum Evaporated Sweetened Condensed Milk Can
- Coconut-Starch Plant-Based Sliced Cheese Line