Continuous Pasta-Filata Mozzarella Shred & Ball

Product family: Pizza IQF Shred & Brine Balls.

Flow: Local Pasture Farms → Vat Coagulation & Whey Drain → Steam Screw Stretcher Filata → Chilled Salt-Brine Tunnel → Optical DICER & Nitrogen Pouch → +2°C Cold Staging Pallet → Foodservice & Pizzerias

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Continuous Pasta-Filata Mozzarella Shred & BallSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Local Pasture Farms → Vat Coagulation & Whey Drain (5.5 s) → Steam Screw Stretcher Filata (6.6 s) → Chilled Salt-Brine Tunnel (8.9 s) → Optical DICER & Nitrogen Pouch (7.0 s) → +2°C Cold Staging Pallet (5.2 s) → Foodservice & Pizzerias.SUPPLIERLocal PastureFarmsI1.20 d1Vat Coagulation &Whey DrainC/T 5.5 sI1.10 d2Steam ScrewStretcher FilataC/T 6.6 sI1.50 d3ChilledSalt-Brine TunnelC/T 8.9 sI0.90 d4Optical DICER &Nitrogen PouchC/T 7.0 sI1.10 d5+2°C Cold StagingPalletC/T 5.2 sI1.40 dCUSTOMERFoodservice &Pizzerias6,500 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Vat Coagulation & Whey Drain5.5 s25 min95%99.1%6,5007,800 (1.20 d)8,987
2. Steam Screw Stretcher Filata6.6 s35 min92%98.4%5,2007,150 (1.10 d)7,047
3. Chilled Salt-Brine Tunnel8.9 s85 min81%97.5%6,5009,750 (1.50 d)4,339
4. Optical DICER & Nitrogen Pouch7.0 s30 min90%97.9%3,2505,850 (0.90 d)6,344
5. +2°C Cold Staging Pallet5.2 s12 min96%99.4%2,6007,150 (1.10 d)9,579

Key figures

Takt time
8.3 s
Lead time
7.20 d
Value-added time
33.2 s
Process cycle efficiency (PCE)
0.009%
Rolled throughput yield (RTY)
92.5%
Customer demand per day
6,500 packs
Line capacity per day
4,339 packs
Bottleneck
Chilled Salt-Brine Tunnel

Reading the bottleneck

The bottleneck is "Chilled Salt-Brine Tunnel": it can process 4,339 packs per day against a demand of 6,500 packs, so it falls short of demand by 33.2%. Once downtime and scrap are counted, its cycle time grows from 8.9 s to 11.3 s, against a takt of 8.3 s. The largest loss at this step is equipment downtime (uptime 81%), about 2.1 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Dairy, UHT & Plant-Based Alt: Dairy, UHT & Plant-Based Alt