12-Ton/Hr Extruded Complete Dry Dog Kibble Line
Product family: 12kg Nitrogen-Sealed Bags.
Flow: Poultry Meal & Grains Silo → Hammer Mill & Vacuum Coater → Pre-Condition & Twin Extrude → Gas Multi-Pass Belt Dryer → Fat & Palatant Vacuum Coat → 12kg Heat-Pinch Bag & Pallet → Pet Specialty & Grocery
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Hammer Mill & Vacuum Coater | 8.6 s | 25 min | 95% | 98.8% | 5,120 | 7,040 (1.10 d) | 8,636 |
| 2. Pre-Condition & Twin Extrude | 10.8 s | 40 min | 90% | 97.5% | 5,120 | 8,320 (1.30 d) | 6,338 |
| 3. Gas Multi-Pass Belt Dryer | 13.7 s | 55 min | 84% | 96.2% | 6,400 | 11,520 (1.80 d) | 4,583 |
| 4. Fat & Palatant Vacuum Coat | 9.1 s | 8 min | 96% | 98.9% | 1,920 | 5,120 (0.80 d) | 8,284 |
| 5. 12kg Heat-Pinch Bag & Pallet | 7.3 s | 10 min | 97% | 99.4% | 1,920 | 7,680 (1.20 d) | 10,434 |
Key figures
- Takt time
- 12.7 s
- Lead time
- 8.00 d
- Value-added time
- 49.5 s
- Process cycle efficiency (PCE)
- 0.008%
- Rolled throughput yield (RTY)
- 91.1%
- Customer demand per day
- 6,400 packs
- Line capacity per day
- 4,583 packs
- Bottleneck
- Gas Multi-Pass Belt Dryer
Reading the bottleneck
The bottleneck is "Gas Multi-Pass Belt Dryer": it can process 4,583 packs per day against a demand of 6,400 packs, so it falls short of demand by 28.4%. Once downtime and scrap are counted, its cycle time grows from 13.7 s to 17.0 s, against a takt of 12.7 s. The largest loss at this step is equipment downtime (uptime 84%), about 2.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Frozen Meals, Retort & Pet Food: Frozen Meals, Retort & Pet Food
- 85g Chunks-in-Gravy Wet Cat Food Retort Pouch
- Fresh Harvest Pea Pod, Blanch & IQF Bagging
- Wood-Fired Stone-Baked Frozen Pizza Assembly
- 20-Ton/Hr Water-Gun Cut Par-Fried French Fries
- Dual-Ovenable CPET Ready-to-Eat Meal Line
- Vacuum Sublimation Freeze-Dried Strawberry Line
- Folded Gyoza & Dumpling Steaming IQF Line
- Vacuum Sterilized Organic Baby Food Glass Jar
- IQF Portion-Control Frozen Smoothie Cubes
- 18-Hour Slow-Simmer Retort Carton Bone Broth
- Food-Grade Ozone-Filtered Party Ice Cube Plant