Folded Gyoza & Dumpling Steaming IQF Line
Product family: 500g Authentic Asian Dumplings.
Flow: Wheat Sheet & Pork/Veg Mix → Continuous Dough Sheet Thin → High-Speed Encrust & Pleat → Direct Steam Gel Tunnel → Blast Spiral Freeze -35°C → Multi-Head Weigh Pillow Bag → Retail & Ethnic Supermarkets
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Continuous Dough Sheet Thin | 2.0 s | 25 min | 95% | 98.8% | 14,400 | 19,800 (1.10 d) | 24,462 |
| 2. High-Speed Encrust & Pleat | 2.5 s | 40 min | 90% | 97.5% | 14,400 | 23,400 (1.30 d) | 17,901 |
| 3. Direct Steam Gel Tunnel | 3.2 s | 55 min | 84% | 96.2% | 18,000 | 32,400 (1.80 d) | 12,803 |
| 4. Blast Spiral Freeze -35°C | 2.2 s | 8 min | 96% | 98.9% | 5,400 | 14,400 (0.80 d) | 22,614 |
| 5. Multi-Head Weigh Pillow Bag | 1.7 s | 10 min | 97% | 99.4% | 5,400 | 21,600 (1.20 d) | 29,493 |
Key figures
- Takt time
- 3.0 s
- Lead time
- 8.00 d
- Value-added time
- 11.6 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 91.1%
- Customer demand per day
- 18,000 packs
- Line capacity per day
- 12,803 packs
- Bottleneck
- Direct Steam Gel Tunnel
Reading the bottleneck
The bottleneck is "Direct Steam Gel Tunnel": it can process 12,803 packs per day against a demand of 18,000 packs, so it falls short of demand by 28.9%. Once downtime and scrap are counted, its cycle time grows from 3.2 s to 4.0 s, against a takt of 3.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Frozen Meals, Retort & Pet Food: Frozen Meals, Retort & Pet Food
- 12-Ton/Hr Extruded Complete Dry Dog Kibble Line
- 85g Chunks-in-Gravy Wet Cat Food Retort Pouch
- Fresh Harvest Pea Pod, Blanch & IQF Bagging
- Wood-Fired Stone-Baked Frozen Pizza Assembly
- 20-Ton/Hr Water-Gun Cut Par-Fried French Fries
- Dual-Ovenable CPET Ready-to-Eat Meal Line
- Vacuum Sublimation Freeze-Dried Strawberry Line
- Vacuum Sterilized Organic Baby Food Glass Jar
- IQF Portion-Control Frozen Smoothie Cubes
- 18-Hour Slow-Simmer Retort Carton Bone Broth
- Food-Grade Ozone-Filtered Party Ice Cube Plant