IQF Portion-Control Frozen Smoothie Cubes
Product family: 450g Pre-Portioned Pouches.
Flow: Aseptic Fruit Purees & Greens → Chilled Recipe Batch Blend → Rotary Cube Pocket Fill → -38°C Cryo Demold & Harden → VFFS Stand-Up Zipper Pouch → Checkweigh & Frozen -20°C → Health Retail & Smoothie Bars
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Chilled Recipe Batch Blend | 2.6 s | 25 min | 95% | 98.8% | 11,200 | 15,400 (1.10 d) | 18,817 |
| 2. Rotary Cube Pocket Fill | 3.3 s | 40 min | 90% | 97.5% | 11,200 | 18,200 (1.30 d) | 13,561 |
| 3. -38°C Cryo Demold & Harden | 4.2 s | 55 min | 84% | 96.2% | 14,000 | 25,200 (1.80 d) | 9,755 |
| 4. VFFS Stand-Up Zipper Pouch | 2.8 s | 8 min | 96% | 98.9% | 4,200 | 11,200 (0.80 d) | 17,768 |
| 5. Checkweigh & Frozen -20°C | 2.2 s | 10 min | 97% | 99.4% | 4,200 | 16,800 (1.20 d) | 22,790 |
Key figures
- Takt time
- 3.9 s
- Lead time
- 8.00 d
- Value-added time
- 15.1 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 91.1%
- Customer demand per day
- 14,000 packs
- Line capacity per day
- 9,755 packs
- Bottleneck
- -38°C Cryo Demold & Harden
Reading the bottleneck
The bottleneck is "-38°C Cryo Demold & Harden": it can process 9,755 packs per day against a demand of 14,000 packs, so it falls short of demand by 30.3%. Once downtime and scrap are counted, its cycle time grows from 4.2 s to 5.2 s, against a takt of 3.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.8 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Frozen Meals, Retort & Pet Food: Frozen Meals, Retort & Pet Food
- 12-Ton/Hr Extruded Complete Dry Dog Kibble Line
- 85g Chunks-in-Gravy Wet Cat Food Retort Pouch
- Fresh Harvest Pea Pod, Blanch & IQF Bagging
- Wood-Fired Stone-Baked Frozen Pizza Assembly
- 20-Ton/Hr Water-Gun Cut Par-Fried French Fries
- Dual-Ovenable CPET Ready-to-Eat Meal Line
- Vacuum Sublimation Freeze-Dried Strawberry Line
- Folded Gyoza & Dumpling Steaming IQF Line
- Vacuum Sterilized Organic Baby Food Glass Jar
- 18-Hour Slow-Simmer Retort Carton Bone Broth
- Food-Grade Ozone-Filtered Party Ice Cube Plant