85g Chunks-in-Gravy Wet Cat Food Retort Pouch
Product family: 400-ppm Rotary Retort Line.
Flow: Fresh Meat Trims & Plasma → Emulsify & Steam Tunnel Cook → Rotary Guillotine Chunk Cut → Multi-Head Meat + Gravy Fill → Ultrasonic Jaw Clean Seal → Rotary Tray Batch Autoclave → Global Pet Retail Chains
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Emulsify & Steam Tunnel Cook | 1.2 s | 25 min | 95% | 98.8% | 46,400 | 63,800 (1.10 d) | 61,889 |
| 2. Rotary Guillotine Chunk Cut | 1.2 s | 40 min | 90% | 97.5% | 46,400 | 75,400 (1.30 d) | 57,038 |
| 3. Multi-Head Meat + Gravy Fill | 1.5 s | 55 min | 84% | 96.2% | 58,000 | 104,400 (1.80 d) | 41,859 |
| 4. Ultrasonic Jaw Clean Seal | 1.2 s | 8 min | 96% | 98.9% | 17,400 | 46,400 (0.80 d) | 62,821 |
| 5. Rotary Tray Batch Autoclave | 1.2 s | 10 min | 97% | 99.4% | 17,400 | 69,600 (1.20 d) | 63,475 |
Key figures
- Takt time
- 1.4 s
- Lead time
- 8.00 d
- Value-added time
- 6.3 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 91.1%
- Customer demand per day
- 58,000 packs
- Line capacity per day
- 41,859 packs
- Bottleneck
- Multi-Head Meat + Gravy Fill
Reading the bottleneck
The bottleneck is "Multi-Head Meat + Gravy Fill": it can process 41,859 packs per day against a demand of 58,000 packs, so it falls short of demand by 27.8%. Once downtime and scrap are counted, its cycle time grows from 1.5 s to 1.9 s, against a takt of 1.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Frozen Meals, Retort & Pet Food: Frozen Meals, Retort & Pet Food
- 12-Ton/Hr Extruded Complete Dry Dog Kibble Line
- Fresh Harvest Pea Pod, Blanch & IQF Bagging
- Wood-Fired Stone-Baked Frozen Pizza Assembly
- 20-Ton/Hr Water-Gun Cut Par-Fried French Fries
- Dual-Ovenable CPET Ready-to-Eat Meal Line
- Vacuum Sublimation Freeze-Dried Strawberry Line
- Folded Gyoza & Dumpling Steaming IQF Line
- Vacuum Sterilized Organic Baby Food Glass Jar
- IQF Portion-Control Frozen Smoothie Cubes
- 18-Hour Slow-Simmer Retort Carton Bone Broth
- Food-Grade Ozone-Filtered Party Ice Cube Plant