Food-Grade Ozone-Filtered Party Ice Cube Plant
Product family: 2kg & 5kg Retail Poly Ice Bags.
Flow: Municipal RO Water Supply → RO & UV Water Sanitation → -18°C Tube Ice Harvest → Screw Dewater & Screen Fines → Auto Poly Form-Fill-Seal → Palletize into -12°C Vault → Convenience & Summer Retail
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. RO & UV Water Sanitation | 1.7 s | 25 min | 95% | 98.8% | 17,600 | 24,200 (1.10 d) | 28,779 |
| 2. -18°C Tube Ice Harvest | 2.1 s | 40 min | 90% | 97.5% | 17,600 | 28,600 (1.30 d) | 21,311 |
| 3. Screw Dewater & Screen Fines | 2.7 s | 55 min | 84% | 96.2% | 22,000 | 39,600 (1.80 d) | 15,174 |
| 4. Auto Poly Form-Fill-Seal | 1.8 s | 8 min | 96% | 98.9% | 6,600 | 17,600 (0.80 d) | 27,639 |
| 5. Palletize into -12°C Vault | 1.4 s | 10 min | 97% | 99.4% | 6,600 | 26,400 (1.20 d) | 35,812 |
Key figures
- Takt time
- 2.5 s
- Lead time
- 8.00 d
- Value-added time
- 9.7 s
- Process cycle efficiency (PCE)
- 0.002%
- Rolled throughput yield (RTY)
- 91.1%
- Customer demand per day
- 22,000 packs
- Line capacity per day
- 15,174 packs
- Bottleneck
- Screw Dewater & Screen Fines
Reading the bottleneck
The bottleneck is "Screw Dewater & Screen Fines": it can process 15,174 packs per day against a demand of 22,000 packs, so it falls short of demand by 31.0%. Once downtime and scrap are counted, its cycle time grows from 2.7 s to 3.3 s, against a takt of 2.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.5 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Frozen Meals, Retort & Pet Food: Frozen Meals, Retort & Pet Food
- 12-Ton/Hr Extruded Complete Dry Dog Kibble Line
- 85g Chunks-in-Gravy Wet Cat Food Retort Pouch
- Fresh Harvest Pea Pod, Blanch & IQF Bagging
- Wood-Fired Stone-Baked Frozen Pizza Assembly
- 20-Ton/Hr Water-Gun Cut Par-Fried French Fries
- Dual-Ovenable CPET Ready-to-Eat Meal Line
- Vacuum Sublimation Freeze-Dried Strawberry Line
- Folded Gyoza & Dumpling Steaming IQF Line
- Vacuum Sterilized Organic Baby Food Glass Jar
- IQF Portion-Control Frozen Smoothie Cubes
- 18-Hour Slow-Simmer Retort Carton Bone Broth