Dual-Ovenable CPET Ready-to-Eat Meal Line

Product family: 400g Chilled/Frozen Entrees.

Flow: Central Steam Kettle Chefs → Steam Jacket Kettle Cook → Multi-Component Servo Deposit → Lidding Peel Film & Blast Chill → X-Ray & Cardstock Sleeve → Crate Sort & +2°C / -18°C Dock → Grocery Chilled/Frozen

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Dual-Ovenable CPET Ready-to-Eat Meal LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Central Steam Kettle Chefs → Steam Jacket Kettle Cook (2.3 s) → Multi-Component Servo Deposit (2.9 s) → Lidding Peel Film & Blast Chill (3.6 s) → X-Ray & Cardstock Sleeve (2.4 s) → Crate Sort & +2°C / -18°C Dock (2.0 s) → Grocery Chilled/Frozen.SUPPLIERCentral SteamKettle ChefsI1.10 d1Steam JacketKettle CookC/T 2.3 sI1.30 d2Multi-ComponentServo DepositC/T 2.9 sI1.80 d3Lidding Peel Film& Blast ChillC/T 3.6 sI0.80 d4X-Ray & CardstockSleeveC/T 2.4 sI1.20 d5Crate Sort & +2°C/ -18°C DockC/T 2.0 sI1.80 dCUSTOMERGroceryChilled/Frozen16,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Steam Jacket Kettle Cook2.3 s25 min95%98.8%12,80017,600 (1.10 d)21,272
2. Multi-Component Servo Deposit2.9 s40 min90%97.5%12,80020,800 (1.30 d)15,432
3. Lidding Peel Film & Blast Chill3.6 s55 min84%96.2%16,00028,800 (1.80 d)11,380
4. X-Ray & Cardstock Sleeve2.4 s8 min96%98.9%4,80012,800 (0.80 d)20,729
5. Crate Sort & +2°C / -18°C Dock2.0 s10 min97%99.4%4,80019,200 (1.20 d)25,069

Key figures

Takt time
3.4 s
Lead time
8.00 d
Value-added time
13.2 s
Process cycle efficiency (PCE)
0.003%
Rolled throughput yield (RTY)
91.1%
Customer demand per day
16,000 packs
Line capacity per day
11,380 packs
Bottleneck
Lidding Peel Film & Blast Chill

Reading the bottleneck

The bottleneck is "Lidding Peel Film & Blast Chill": it can process 11,380 packs per day against a demand of 16,000 packs, so it falls short of demand by 28.9%. Once downtime and scrap are counted, its cycle time grows from 3.6 s to 4.5 s, against a takt of 3.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.7 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.