Fresh Harvest Pea Pod, Blanch & IQF Bagging
Product family: 1kg Retail Poly-Pouch Peas.
Flow: Field Pea Viners → Air-Cleaner & Flotation Wash → Steam Blanch & Cool Quench → Fluidized Belt IQF Freeze → Optical Defect & Brine Grade → Auto Form-Fill-Seal -20°C → Cold Retail Distribution
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Air-Cleaner & Flotation Wash | 2.3 s | 25 min | 95% | 98.8% | 19,200 | 26,400 (1.10 d) | 32,290 |
| 2. Steam Blanch & Cool Quench | 2.9 s | 40 min | 90% | 97.5% | 19,200 | 31,200 (1.30 d) | 23,602 |
| 3. Fluidized Belt IQF Freeze | 3.6 s | 55 min | 84% | 96.2% | 24,000 | 43,200 (1.80 d) | 17,441 |
| 4. Optical Defect & Brine Grade | 2.4 s | 8 min | 96% | 98.9% | 7,200 | 19,200 (0.80 d) | 31,411 |
| 5. Auto Form-Fill-Seal -20°C | 2.0 s | 10 min | 97% | 99.4% | 7,200 | 28,800 (1.20 d) | 38,085 |
Key figures
- Takt time
- 3.4 s
- Lead time
- 8.00 d
- Value-added time
- 13.2 s
- Process cycle efficiency (PCE)
- 0.002%
- Rolled throughput yield (RTY)
- 91.1%
- Customer demand per day
- 24,000 packs
- Line capacity per day
- 17,441 packs
- Bottleneck
- Fluidized Belt IQF Freeze
Reading the bottleneck
The bottleneck is "Fluidized Belt IQF Freeze": it can process 17,441 packs per day against a demand of 24,000 packs, so it falls short of demand by 27.3%. Once downtime and scrap are counted, its cycle time grows from 3.6 s to 4.5 s, against a takt of 3.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Frozen Meals, Retort & Pet Food: Frozen Meals, Retort & Pet Food
- 12-Ton/Hr Extruded Complete Dry Dog Kibble Line
- 85g Chunks-in-Gravy Wet Cat Food Retort Pouch
- Wood-Fired Stone-Baked Frozen Pizza Assembly
- 20-Ton/Hr Water-Gun Cut Par-Fried French Fries
- Dual-Ovenable CPET Ready-to-Eat Meal Line
- Vacuum Sublimation Freeze-Dried Strawberry Line
- Folded Gyoza & Dumpling Steaming IQF Line
- Vacuum Sterilized Organic Baby Food Glass Jar
- IQF Portion-Control Frozen Smoothie Cubes
- 18-Hour Slow-Simmer Retort Carton Bone Broth
- Food-Grade Ozone-Filtered Party Ice Cube Plant