University Campus Summer Room Turnaround

Product family: 3,000 Dorm Rooms in 14 Days.

Flow: Campus Facilities & Paint → Move-Out Inventory & Key → Maintenance Paint & Plumbing → Deep Carpet Steam & Mattress → Inspector Checklist QR Sign → Key-Packet Move-In Booth → Incoming Autumn Freshmen

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: University Campus Summer Room TurnaroundSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Campus Facilities & Paint → Move-Out Inventory & Key (72.0 s) → Maintenance Paint & Plumbing (86.0 s) → Deep Carpet Steam & Mattress (120 s) → Inspector Checklist QR Sign (77.0 s) → Key-Packet Move-In Booth (59.0 s) → Incoming Autumn Freshmen.SUPPLIERCampusFacilities &PaintI0.50 d1Move-OutInventory & KeyC/T 72.0 sI0.70 d2Maintenance Paint& PlumbingC/T 86.0 sI1.20 d3Deep Carpet Steam& MattressC/T 120 sI0.45 d4InspectorChecklist QR SignC/T 77.0 sI0.25 d5Key-PacketMove-In BoothC/T 59.0 sI0.40 dCUSTOMERIncoming AutumnFreshmen240 / rooms

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Move-Out Inventory & Key72.0 s3 min97%98.5%48120 (0.50 d)346
2. Maintenance Paint & Plumbing86.0 s5 min95%98.1%48168 (0.70 d)276
3. Deep Carpet Steam & Mattress120 s8 min88%91.0%36288 (1.20 d)159
4. Inspector Checklist QR Sign77.0 s2 min96%96.5%24108 (0.45 d)310
5. Key-Packet Move-In Booth59.0 s2 min99%99.2%2460 (0.25 d)429

Key figures

Takt time
113 s
Lead time
3.52 d
Value-added time
414 s
Process cycle efficiency (PCE)
0.44%
Rolled throughput yield (RTY)
84.2%
Customer demand per day
240 rooms
Line capacity per day
159 rooms
Bottleneck
Deep Carpet Steam & Mattress

Reading the bottleneck

The bottleneck is "Deep Carpet Steam & Mattress": it can process 159 rooms per day against a demand of 240 rooms, so it falls short of demand by 33.8%. Once downtime and scrap are counted, its cycle time grows from 120 s to 150 s, against a takt of 113 s. The largest loss at this step is equipment downtime (uptime 88%), about 16.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.