Precision ANSI/DIN Heavy Conveyor Roller Chain

Product family: Shot-Peened Fatigue Chains.

Flow: Cold Rolled Strip Steel → Progressive Link Blank Stamp → Carbonitride Heat Furnace → Bushing Seam & Solid Roll → Auto High-Speed Chain Pin → 30% Proof Tension Pre-Stretch → Food & Logistics OEMs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Precision ANSI/DIN Heavy Conveyor Roller ChainSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Cold Rolled Strip Steel → Progressive Link Blank Stamp (21.6 s) → Carbonitride Heat Furnace (25.2 s) → Bushing Seam & Solid Roll (32.1 s) → Auto High-Speed Chain Pin (22.8 s) → 30% Proof Tension Pre-Stretch (16.8 s) → Food & Logistics OEMs.SUPPLIERCold RolledStrip SteelI2.20 d1Progressive LinkBlank StampC/T 21.6 sI1.80 d2Carbonitride HeatFurnaceC/T 25.2 sI2.40 d3Bushing Seam &Solid RollC/T 32.1 sI1.50 d4Auto High-SpeedChain PinC/T 22.8 sI0.80 d530% Proof TensionPre-StretchC/T 16.8 sI2.00 dCUSTOMERFood &Logistics OEMs1,800 / meters

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Progressive Link Blank Stamp21.6 s65 min90%98.8%3,6003,960 (2.20 d)2,143
2. Carbonitride Heat Furnace25.2 s45 min91%97.6%2,7003,240 (1.80 d)1,840
3. Bushing Seam & Solid Roll32.1 s50 min84%96.1%2,7004,320 (2.40 d)1,308
4. Auto High-Speed Chain Pin22.8 s20 min93%98.4%1,8002,700 (1.50 d)2,119
5. 30% Proof Tension Pre-Stretch16.8 s12 min97%99.6%9001,440 (0.80 d)3,023

Key figures

Takt time
30.0 s
Lead time
10.7 d
Value-added time
119 s
Process cycle efficiency (PCE)
0.021%
Rolled throughput yield (RTY)
90.8%
Customer demand per day
1,800 meters
Line capacity per day
1,308 meters
Bottleneck
Bushing Seam & Solid Roll

Reading the bottleneck

The bottleneck is "Bushing Seam & Solid Roll": it can process 1,308 meters per day against a demand of 1,800 meters, so it falls short of demand by 27.4%. Once downtime and scrap are counted, its cycle time grows from 32.1 s to 39.8 s, against a takt of 30.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 6.1 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.