Hot-Forged Lead-Free Brass Radiant Manifold

Product family: CW510L HVAC Heating Manifolds.

Flow: Brass rod supplier → 1000T Closed-Die Hot Forge → Transfer Machine Thread & Bore → Shot-Blast & Nickel Flash → EPDM Flow-Meter Valve Fit → 10-Bar Bubble Decay & Pack → European Hydronic Plumbing

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Hot-Forged Lead-Free Brass Radiant ManifoldSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Brass rod supplier → 1000T Closed-Die Hot Forge (41.0 s) → Transfer Machine Thread & Bore (48.0 s) → Shot-Blast & Nickel Flash (61.0 s) → EPDM Flow-Meter Valve Fit (43.0 s) → 10-Bar Bubble Decay & Pack (31.8 s) → European Hydronic Plumbing.SUPPLIERBrass rodsupplierI2.20 d11000T Closed-DieHot ForgeC/T 41.0 sI1.80 d2Transfer MachineThread & BoreC/T 48.0 sI2.40 d3Shot-Blast &Nickel FlashC/T 61.0 sI1.50 d4EPDM Flow-MeterValve FitC/T 43.0 sI0.80 d510-Bar BubbleDecay & PackC/T 31.8 sI2.00 dCUSTOMEREuropeanHydronic…950 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 1000T Closed-Die Hot Forge41.0 s65 min90%98.8%1,9002,090 (2.20 d)1,129
2. Transfer Machine Thread & Bore48.0 s45 min91%97.6%1,4251,710 (1.80 d)966
3. Shot-Blast & Nickel Flash61.0 s50 min84%96.1%1,4252,280 (2.40 d)688
4. EPDM Flow-Meter Valve Fit43.0 s20 min93%98.4%9501,425 (1.50 d)1,124
5. 10-Bar Bubble Decay & Pack31.8 s12 min97%99.6%475760 (0.80 d)1,597

Key figures

Takt time
56.8 s
Lead time
10.7 d
Value-added time
225 s
Process cycle efficiency (PCE)
0.039%
Rolled throughput yield (RTY)
90.8%
Customer demand per day
950 units
Line capacity per day
688 units
Bottleneck
Shot-Blast & Nickel Flash

Reading the bottleneck

The bottleneck is "Shot-Blast & Nickel Flash": it can process 688 units per day against a demand of 950 units, so it falls short of demand by 27.6%. Once downtime and scrap are counted, its cycle time grows from 61.0 s to 75.6 s, against a takt of 56.8 s. The largest loss at this step is equipment downtime (uptime 84%), about 11.6 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.