Hot-Forged Lead-Free Brass Radiant Manifold
Product family: CW510L HVAC Heating Manifolds.
Flow: Brass rod supplier → 1000T Closed-Die Hot Forge → Transfer Machine Thread & Bore → Shot-Blast & Nickel Flash → EPDM Flow-Meter Valve Fit → 10-Bar Bubble Decay & Pack → European Hydronic Plumbing
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 1000T Closed-Die Hot Forge | 41.0 s | 65 min | 90% | 98.8% | 1,900 | 2,090 (2.20 d) | 1,129 |
| 2. Transfer Machine Thread & Bore | 48.0 s | 45 min | 91% | 97.6% | 1,425 | 1,710 (1.80 d) | 966 |
| 3. Shot-Blast & Nickel Flash | 61.0 s | 50 min | 84% | 96.1% | 1,425 | 2,280 (2.40 d) | 688 |
| 4. EPDM Flow-Meter Valve Fit | 43.0 s | 20 min | 93% | 98.4% | 950 | 1,425 (1.50 d) | 1,124 |
| 5. 10-Bar Bubble Decay & Pack | 31.8 s | 12 min | 97% | 99.6% | 475 | 760 (0.80 d) | 1,597 |
Key figures
- Takt time
- 56.8 s
- Lead time
- 10.7 d
- Value-added time
- 225 s
- Process cycle efficiency (PCE)
- 0.039%
- Rolled throughput yield (RTY)
- 90.8%
- Customer demand per day
- 950 units
- Line capacity per day
- 688 units
- Bottleneck
- Shot-Blast & Nickel Flash
Reading the bottleneck
The bottleneck is "Shot-Blast & Nickel Flash": it can process 688 units per day against a demand of 950 units, so it falls short of demand by 27.6%. Once downtime and scrap are counted, its cycle time grows from 61.0 s to 75.6 s, against a takt of 56.8 s. The largest loss at this step is equipment downtime (uptime 84%), about 11.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Bearings, Gears & Precision Fasteners: Bearings, Gears & Precision Fasteners
- Case-Hardened Automotive Tapered Roller Bearing
- Nickel-Alloy 718 High-Temp 12-Point Aero Bolt
- 5-Flute AlTiN Coated Solid Carbide Endmill
- Pre-Loaded C3 Precision Ground Ball Screw
- Induction-Hardened 4-Cyl Forged Crankshaft
- Sub-Millimeter Titanium Orthopedic Bone Screw
- Powder-Metal Sintered Variable Cam Phaser Rotor
- Parabolic Taper-Rolled Truck Suspension Leaf
- Precision ANSI/DIN Heavy Conveyor Roller Chain
- ASME B16.5 Forged 316L Weld-Neck Pipe Flange
- Active Magnetic Bearing Turbo-Expander Cartridge