ASME B16.5 Forged 316L Weld-Neck Pipe Flange

Product family: High-Pressure Piping Flanges.

Flow: European Forging Houses → Ring Roll Forging & Sol-Anneal → CNC Raised-Face Phonograph → Multi-Spindle Bolt-Hole Drill → PMI Alloy Laser Stamp → Passivate Dip & Pallet Band → Oil, Gas & Pharma Piping

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: ASME B16.5 Forged 316L Weld-Neck Pipe FlangeSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. European Forging Houses → Ring Roll Forging & Sol-Anneal (52.0 s) → CNC Raised-Face Phonograph (60.0 s) → Multi-Spindle Bolt-Hole Drill (77.0 s) → PMI Alloy Laser Stamp (55.0 s) → Passivate Dip & Pallet Band (40.0 s) → Oil, Gas & Pharma Piping.SUPPLIEREuropeanForging HousesI2.20 d1Ring Roll Forging& Sol-AnnealC/T 52.0 sI1.80 d2CNC Raised-FacePhonographC/T 60.0 sI2.40 d3Multi-SpindleBolt-Hole DrillC/T 77.0 sI1.50 d4PMI Alloy LaserStampC/T 55.0 sI0.80 d5Passivate Dip &Pallet BandC/T 40.0 sI2.00 dCUSTOMEROil, Gas &Pharma Piping750 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Ring Roll Forging & Sol-Anneal52.0 s65 min90%98.8%1,5001,650 (2.20 d)890
2. CNC Raised-Face Phonograph60.0 s45 min91%97.6%1,1251,350 (1.80 d)773
3. Multi-Spindle Bolt-Hole Drill77.0 s50 min84%96.1%1,1251,800 (2.40 d)545
4. PMI Alloy Laser Stamp55.0 s20 min93%98.4%7501,125 (1.50 d)879
5. Passivate Dip & Pallet Band40.0 s12 min97%99.6%375600 (0.80 d)1,269

Key figures

Takt time
72.0 s
Lead time
10.7 d
Value-added time
284 s
Process cycle efficiency (PCE)
0.049%
Rolled throughput yield (RTY)
90.8%
Customer demand per day
750 parts
Line capacity per day
545 parts
Bottleneck
Multi-Spindle Bolt-Hole Drill

Reading the bottleneck

The bottleneck is "Multi-Spindle Bolt-Hole Drill": it can process 545 parts per day against a demand of 750 parts, so it falls short of demand by 27.3%. Once downtime and scrap are counted, its cycle time grows from 77.0 s to 95.4 s, against a takt of 72.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 14.7 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.