Active Magnetic Bearing Turbo-Expander Cartridge

Product family: Oil-Free Levitation Bearings.

Flow: Silicon steel supplier → Laser Cut Stator Stack Bond → High-Temp Polyimide Coil Wind → Vacuum Potting Epoxy Bake → EDM Air-Gap Touch-Up Grind → 5-Axis Levitation Loop Test → Cryogenic & Gas Compressors

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Active Magnetic Bearing Turbo-Expander CartridgeSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Silicon steel supplier → Laser Cut Stator Stack Bond (884 s) → High-Temp Polyimide Coil Wind (1,031 s) → Vacuum Potting Epoxy Bake (1,313 s) → EDM Air-Gap Touch-Up Grind (933 s) → 5-Axis Levitation Loop Test (687 s) → Cryogenic & Gas Compressors.SUPPLIERSilicon steelsupplierI2.18 d1Laser Cut StatorStack BondC/T 884 sI1.82 d2High-TempPolyimide Coil…C/T 1,031 sI2.41 d3Vacuum PottingEpoxy BakeC/T 1,313 sI1.50 d4EDM Air-GapTouch-Up GrindC/T 933 sI0.82 d55-Axis LevitationLoop TestC/T 687 sI2.00 dCUSTOMERCryogenic & GasCompressors22 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Laser Cut Stator Stack Bond884 s65 min90%98.8%4448 (2.18 d)25
2. High-Temp Polyimide Coil Wind1,031 s45 min91%97.6%3340 (1.82 d)22
3. Vacuum Potting Epoxy Bake1,313 s50 min84%96.1%3353 (2.41 d)15
4. EDM Air-Gap Touch-Up Grind933 s20 min93%98.4%2233 (1.50 d)25
5. 5-Axis Levitation Loop Test687 s12 min97%99.6%1118 (0.82 d)36

Key figures

Takt time
1,227 s
Lead time
10.9 d
Value-added time
4,848 s
Process cycle efficiency (PCE)
1.6%
Rolled throughput yield (RTY)
90.8%
Customer demand per day
22 units
Line capacity per day
15 units
Bottleneck
Vacuum Potting Epoxy Bake

Reading the bottleneck

The bottleneck is "Vacuum Potting Epoxy Bake": it can process 15 units per day against a demand of 22 units, so it falls short of demand by 30.1%. Once downtime and scrap are counted, its cycle time grows from 1,313 s to 1,627 s, against a takt of 1,227 s. The largest loss at this step is equipment downtime (uptime 84%), about 250 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.