Sub-Millimeter Titanium Orthopedic Bone Screw
Product family: Swiss-Turned Dental & Spine Screws.
Flow: Medical titanium supplier → Multi-Channel Swiss Turn → Star-Drive Broach → Ultrasonic Degrease & Passiv → Anodize Color Size Code → Vision Thread & Burrs 100% → MedTech Orthopedic Plants
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Multi-Channel Swiss Turn | 11.2 s | 65 min | 90% | 98.8% | 10,400 | 11,440 (2.20 d) | 6,276 |
| 2. Star-Drive Broach | 13.1 s | 45 min | 91% | 97.6% | 7,800 | 9,360 (1.80 d) | 5,370 |
| 3. Ultrasonic Degrease & Passiv | 16.7 s | 50 min | 84% | 96.1% | 7,800 | 12,480 (2.40 d) | 3,819 |
| 4. Anodize Color Size Code | 11.8 s | 20 min | 93% | 98.4% | 5,200 | 7,800 (1.50 d) | 6,189 |
| 5. Vision Thread & Burrs 100% | 8.7 s | 12 min | 97% | 99.6% | 2,600 | 4,160 (0.80 d) | 8,835 |
Key figures
- Takt time
- 15.6 s
- Lead time
- 10.7 d
- Value-added time
- 61.5 s
- Process cycle efficiency (PCE)
- 0.007%
- Rolled throughput yield (RTY)
- 90.8%
- Customer demand per day
- 5,200 parts
- Line capacity per day
- 3,819 parts
- Bottleneck
- Ultrasonic Degrease & Passiv
Reading the bottleneck
The bottleneck is "Ultrasonic Degrease & Passiv": it can process 3,819 parts per day against a demand of 5,200 parts, so it falls short of demand by 26.6%. Once downtime and scrap are counted, its cycle time grows from 16.7 s to 20.7 s, against a takt of 15.6 s. The largest loss at this step is equipment downtime (uptime 84%), about 3.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Bearings, Gears & Precision Fasteners: Bearings, Gears & Precision Fasteners
- Case-Hardened Automotive Tapered Roller Bearing
- Nickel-Alloy 718 High-Temp 12-Point Aero Bolt
- 5-Flute AlTiN Coated Solid Carbide Endmill
- Pre-Loaded C3 Precision Ground Ball Screw
- Induction-Hardened 4-Cyl Forged Crankshaft
- Hot-Forged Lead-Free Brass Radiant Manifold
- Powder-Metal Sintered Variable Cam Phaser Rotor
- Parabolic Taper-Rolled Truck Suspension Leaf
- Precision ANSI/DIN Heavy Conveyor Roller Chain
- ASME B16.5 Forged 316L Weld-Neck Pipe Flange
- Active Magnetic Bearing Turbo-Expander Cartridge