Case-Hardened Automotive Tapered Roller Bearing
Product family: Zero-Noise Wheel Hub Bearings.
Flow: Bearing-steel forge → Ring Forging & Spheroid Anneal → Carburize Salt-Bath Quench → CBN Cup & Cone Superfinish → Crowned Roller Laser Sort → Pre-Load Grease & Acoustic Test → Commercial & EV Axles
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Ring Forging & Spheroid Anneal | 13.9 s | 65 min | 90% | 98.8% | 8,400 | 9,240 (2.20 d) | 5,057 |
| 2. Carburize Salt-Bath Quench | 16.2 s | 45 min | 91% | 97.6% | 6,300 | 7,560 (1.80 d) | 4,342 |
| 3. CBN Cup & Cone Superfinish | 20.6 s | 50 min | 84% | 96.1% | 6,300 | 10,080 (2.40 d) | 3,096 |
| 4. Crowned Roller Laser Sort | 14.7 s | 20 min | 93% | 98.4% | 4,200 | 6,300 (1.50 d) | 4,968 |
| 5. Pre-Load Grease & Acoustic Test | 10.8 s | 12 min | 97% | 99.6% | 2,100 | 3,360 (0.80 d) | 7,117 |
Key figures
- Takt time
- 19.3 s
- Lead time
- 10.7 d
- Value-added time
- 76.2 s
- Process cycle efficiency (PCE)
- 0.009%
- Rolled throughput yield (RTY)
- 90.8%
- Customer demand per day
- 4,200 units
- Line capacity per day
- 3,096 units
- Bottleneck
- CBN Cup & Cone Superfinish
Reading the bottleneck
The bottleneck is "CBN Cup & Cone Superfinish": it can process 3,096 units per day against a demand of 4,200 units, so it falls short of demand by 26.3%. Once downtime and scrap are counted, its cycle time grows from 20.6 s to 25.5 s, against a takt of 19.3 s. The largest loss at this step is equipment downtime (uptime 84%), about 3.9 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Bearings, Gears & Precision Fasteners: Bearings, Gears & Precision Fasteners
- Nickel-Alloy 718 High-Temp 12-Point Aero Bolt
- 5-Flute AlTiN Coated Solid Carbide Endmill
- Pre-Loaded C3 Precision Ground Ball Screw
- Induction-Hardened 4-Cyl Forged Crankshaft
- Hot-Forged Lead-Free Brass Radiant Manifold
- Sub-Millimeter Titanium Orthopedic Bone Screw
- Powder-Metal Sintered Variable Cam Phaser Rotor
- Parabolic Taper-Rolled Truck Suspension Leaf
- Precision ANSI/DIN Heavy Conveyor Roller Chain
- ASME B16.5 Forged 316L Weld-Neck Pipe Flange
- Active Magnetic Bearing Turbo-Expander Cartridge