ATEX Zone-1 Explosion-Proof 250kW Motor

Product family: Flameproof Cast-Iron Motors.

Flow: Cast EN-GJL250 Iron → Flamepath Flange Finish CNC → Form-Wound Copper Coil Insert → Dual-Cycle VPI Mica Bake → Rotor Die-Cast Al & Shaft Fit → ATEX Hydro Overpressure Test → Oil, Gas & Chemical Sites

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: ATEX Zone-1 Explosion-Proof 250kW MotorSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Cast EN-GJL250 Iron → Flamepath Flange Finish CNC (1,148 s) → Form-Wound Copper Coil Insert (1,451 s) → Dual-Cycle VPI Mica Bake (1,823 s) → Rotor Die-Cast Al & Shaft Fit (1,316 s) → ATEX Hydro Overpressure Test (1,013 s) → Oil, Gas & Chemical Sites.SUPPLIERCast EN-GJL250IronI1.69 d1Flamepath FlangeFinish CNCC/T 1,148 sI1.81 d2Form-Wound CopperCoil InsertC/T 1,451 sI2.19 d3Dual-Cycle VPIMica BakeC/T 1,823 sI1.09 d4Rotor Die-Cast Al& Shaft FitC/T 1,316 sI0.81 d5ATEX HydroOverpressure TestC/T 1,013 sI1.50 dCUSTOMEROil, Gas &Chemical Sites32 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Flamepath Flange Finish CNC1,148 s35 min93%98.7%4854 (1.69 d)42
2. Form-Wound Copper Coil Insert1,451 s30 min90%96.9%2658 (1.81 d)31
3. Dual-Cycle VPI Mica Bake1,823 s45 min84%95.5%3270 (2.19 d)23
4. Rotor Die-Cast Al & Shaft Fit1,316 s15 min94%98.3%1335 (1.09 d)36
5. ATEX Hydro Overpressure Test1,013 s8 min96%99.1%626 (0.81 d)48

Key figures

Takt time
1,688 s
Lead time
9.22 d
Value-added time
6,751 s
Process cycle efficiency (PCE)
1.4%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
32 units
Line capacity per day
23 units
Bottleneck
Dual-Cycle VPI Mica Bake

Reading the bottleneck

The bottleneck is "Dual-Cycle VPI Mica Bake": it can process 23 units per day against a demand of 32 units, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 1,823 s to 2,273 s, against a takt of 1,688 s. The largest loss at this step is equipment downtime (uptime 84%), about 347 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.