Pre-Fabricated District Heating Substation Skid

Product family: Plate HX + Telemetry Skids.

Flow: Pump & heat-exchanger suppliers → Skid Steel Weld & Paint → Plate HX & VFD Pump Mount → Orbital SS Pipe & Press-Fit → M-Bus Heat Meter Wire → 16-Bar Flush & Insulation Box → Municipal Energy Networks

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Pre-Fabricated District Heating Substation SkidSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Pump & heat-exchanger suppliers → Skid Steel Weld & Paint (334 s) → Plate HX & VFD Pump Mount (422 s) → Orbital SS Pipe & Press-Fit (530 s) → M-Bus Heat Meter Wire (383 s) → 16-Bar Flush & Insulation Box (295 s) → Municipal Energy Networks.SUPPLIERPump &heat-exchangersuppliersI1.71 d1Skid Steel Weld &PaintC/T 334 sI1.80 d2Plate HX & VFDPump MountC/T 422 sI2.20 d3Orbital SS Pipe &Press-FitC/T 530 sI1.11 d4M-Bus Heat MeterWireC/T 383 sI0.80 d516-Bar Flush &Insulation BoxC/T 295 sI1.51 dCUSTOMERMunicipalEnergy Networks55 / skids

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Skid Steel Weld & Paint334 s35 min93%98.7%8394 (1.71 d)70
2. Plate HX & VFD Pump Mount422 s30 min90%96.9%4499 (1.80 d)51
3. Orbital SS Pipe & Press-Fit530 s45 min84%95.5%55121 (2.20 d)37
4. M-Bus Heat Meter Wire383 s15 min94%98.3%2261 (1.11 d)60
5. 16-Bar Flush & Insulation Box295 s8 min96%99.1%1144 (0.80 d)79

Key figures

Takt time
491 s
Lead time
9.20 d
Value-added time
1,964 s
Process cycle efficiency (PCE)
0.79%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
55 skids
Line capacity per day
37 skids
Bottleneck
Orbital SS Pipe & Press-Fit

Reading the bottleneck

The bottleneck is "Orbital SS Pipe & Press-Fit": it can process 37 skids per day against a demand of 55 skids, so it falls short of demand by 33.1%. Once downtime and scrap are counted, its cycle time grows from 530 s to 661 s, against a takt of 491 s. The largest loss at this step is equipment downtime (uptime 84%), about 101 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.