Forged Stainless Steel Micro-Hydro Pelton Wheel

Product family: High-Head Renewable Runners.

Flow: 13Cr4Ni Martensitic Steel → 5-Axis Twin-Bucket Contour Mill → Die-Penetrant Root Verification → HVOF Sand-Erosion Coat → Optical Profile Gauge Match → ISO 1940 Dynamic Balance → Alpine Micro-Hydro Utilities

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Forged Stainless Steel Micro-Hydro Pelton WheelSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. 13Cr4Ni Martensitic Steel → 5-Axis Twin-Bucket Contour Mill (2,295 s) → Die-Penetrant Root Verification (2,903 s) → HVOF Sand-Erosion Coat (3,645 s) → Optical Profile Gauge Match (2,633 s) → ISO 1940 Dynamic Balance (2,025 s) → Alpine Micro-Hydro Utilities.SUPPLIER13Cr4NiMartensiticSteelI1.75 d15-AxisTwin-Bucket…C/T 2,295 sI1.75 d2Die-PenetrantRoot VerificationC/T 2,903 sI2.25 d3HVOF Sand-ErosionCoatC/T 3,645 sI1.13 d4Optical ProfileGauge MatchC/T 2,633 sI0.75 d5ISO 1940 DynamicBalanceC/T 2,025 sI1.50 dCUSTOMERAlpineMicro-Hydro…8 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 5-Axis Twin-Bucket Contour Mill2,295 s35 min93%98.7%1214 (1.75 d)10
2. Die-Penetrant Root Verification2,903 s30 min90%96.9%614 (1.75 d)7
3. HVOF Sand-Erosion Coat3,645 s45 min84%95.5%818 (2.25 d)5
4. Optical Profile Gauge Match2,633 s15 min94%98.3%39 (1.13 d)9
5. ISO 1940 Dynamic Balance2,025 s8 min96%99.1%26 (0.75 d)12

Key figures

Takt time
3,375 s
Lead time
9.63 d
Value-added time
13,501 s
Process cycle efficiency (PCE)
5.2%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
8 parts
Line capacity per day
5 parts
Bottleneck
HVOF Sand-Erosion Coat

Reading the bottleneck

The bottleneck is "HVOF Sand-Erosion Coat": it can process 5 parts per day against a demand of 8 parts, so it falls short of demand by 33.2%. Once downtime and scrap are counted, its cycle time grows from 3,645 s to 4,544 s, against a takt of 3,375 s. The largest loss at this step is equipment downtime (uptime 84%), about 694 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.