Copper Foil Winding 2MVA Transformer Coil

Product family: Resin-Cast Medium-Voltage Coils.

Flow: Electrolytic copper supplier → CNC Strip Slit & Argon TIG Tap → Layer-by-Layer Foil + Aramid Wind → Vacuum Casting Epoxy Mold → Autoclave Ramp Gel & Cure → Partial Discharge <5pC Check → Transformer Substations

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Copper Foil Winding 2MVA Transformer CoilSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Electrolytic copper supplier → CNC Strip Slit & Argon TIG Tap (765 s) → Layer-by-Layer Foil + Aramid Wind (968 s) → Vacuum Casting Epoxy Mold (1,215 s) → Autoclave Ramp Gel & Cure (878 s) → Partial Discharge <5pC Check (675 s) → Transformer Substations.SUPPLIERElectrolyticcopper supplierI1.71 d1CNC Strip Slit &Argon TIG TapC/T 765 sI1.79 d2Layer-by-LayerFoil + Aramid…C/T 968 sI2.21 d3Vacuum CastingEpoxy MoldC/T 1,215 sI1.10 d4Autoclave RampGel & CureC/T 878 sI0.79 d5Partial Discharge<5pC CheckC/T 675 sI1.50 dCUSTOMERTransformerSubstations48 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. CNC Strip Slit & Argon TIG Tap765 s35 min93%98.7%7282 (1.71 d)63
2. Layer-by-Layer Foil + Aramid Wind968 s30 min90%96.9%3886 (1.79 d)47
3. Vacuum Casting Epoxy Mold1,215 s45 min84%95.5%48106 (2.21 d)34
4. Autoclave Ramp Gel & Cure878 s15 min94%98.3%1953 (1.10 d)54
5. Partial Discharge <5pC Check675 s8 min96%99.1%1038 (0.79 d)73

Key figures

Takt time
1,125 s
Lead time
9.19 d
Value-added time
4,501 s
Process cycle efficiency (PCE)
0.91%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
48 units
Line capacity per day
34 units
Bottleneck
Vacuum Casting Epoxy Mold

Reading the bottleneck

The bottleneck is "Vacuum Casting Epoxy Mold": it can process 34 units per day against a demand of 48 units, so it falls short of demand by 29.4%. Once downtime and scrap are counted, its cycle time grows from 1,215 s to 1,515 s, against a takt of 1,125 s. The largest loss at this step is equipment downtime (uptime 84%), about 231 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Electric Motors, HVAC & Heat Transfer: Electric Motors, HVAC & Heat Transfer