800kW Magnetic-Bearing Centrifugal Chiller
Product family: R1234ze Oil-Free HVAC Chillers.
Flow: Magnetic-bearing compressor supplier → Copper-Tube Shell Evap Roll → Orbital Pipe & Brazing Deck → Turbo Compressor Manifold Fit → VFD Cabinet & Nitrogen Hold → AHRI Part-Load Calorimeter → Data Center Cooling Plants
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Copper-Tube Shell Evap Roll | 3,060 s | 35 min | 93% | 98.7% | 9 | 10 (1.67 d) | 8 |
| 2. Orbital Pipe & Brazing Deck | 3,870 s | 30 min | 90% | 96.9% | 5 | 11 (1.83 d) | 6 |
| 3. Turbo Compressor Manifold Fit | 4,860 s | 45 min | 84% | 95.5% | 6 | 13 (2.17 d) | 4 |
| 4. VFD Cabinet & Nitrogen Hold | 3,510 s | 15 min | 94% | 98.3% | 2 | 7 (1.17 d) | 6 |
| 5. AHRI Part-Load Calorimeter | 2,700 s | 8 min | 96% | 99.1% | 1 | 5 (0.83 d) | 9 |
Key figures
- Takt time
- 4,500 s
- Lead time
- 9.83 d
- Value-added time
- 18,000 s
- Process cycle efficiency (PCE)
- 6.8%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 6 units
- Line capacity per day
- 4 units
- Bottleneck
- Turbo Compressor Manifold Fit
Reading the bottleneck
The bottleneck is "Turbo Compressor Manifold Fit": it can process 4 units per day against a demand of 6 units, so it falls short of demand by 33.2%. Once downtime and scrap are counted, its cycle time grows from 4,860 s to 6,058 s, against a takt of 4,500 s. The largest loss at this step is equipment downtime (uptime 84%), about 926 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Electric Motors, HVAC & Heat Transfer: Electric Motors, HVAC & Heat Transfer
- Compact Brushless Industrial Servo Motor
- Laser-Welded 316L Plate Heat Exchanger
- Pultruded FRP Crossflow Industrial Cooling Tower
- ATEX Zone-1 Explosion-Proof 250kW Motor
- Fire-Tube Condensing 5-Ton Steam Boiler
- Commercial Heat-Recovery VRF Outdoor Unit
- Alu-Silica Desiccant Enthalpy Rotary Wheel
- Copper Foil Winding 2MVA Transformer Coil
- Microchannel V-Bank Adiabatic Air Condenser
- Pre-Fabricated District Heating Substation Skid
- Forged Stainless Steel Micro-Hydro Pelton Wheel