Alu-Silica Desiccant Enthalpy Rotary Wheel
Product family: 90% Heat-Recovery AHU Wheels.
Flow: Thin-Gauge Al Foil → Foil Corrugation & Molecular Coat → Laser-Guided Rotor Spiral Wind → Hub Spoke Weld & Brush Seals → Rim Drive Motor Tension Rig → Leakage & Latent Efficiency QC → Hospital & Cleanroom AHUs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Foil Corrugation & Molecular Coat | 387 s | 35 min | 93% | 98.7% | 143 | 162 (1.71 d) | 125 |
| 2. Laser-Guided Rotor Spiral Wind | 489 s | 30 min | 90% | 96.9% | 76 | 171 (1.80 d) | 92 |
| 3. Hub Spoke Weld & Brush Seals | 614 s | 45 min | 84% | 95.5% | 95 | 209 (2.20 d) | 67 |
| 4. Rim Drive Motor Tension Rig | 443 s | 15 min | 94% | 98.3% | 38 | 105 (1.11 d) | 108 |
| 5. Leakage & Latent Efficiency QC | 341 s | 8 min | 96% | 99.1% | 19 | 76 (0.80 d) | 144 |
Key figures
- Takt time
- 568 s
- Lead time
- 9.16 d
- Value-added time
- 2,274 s
- Process cycle efficiency (PCE)
- 0.46%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 95 units
- Line capacity per day
- 67 units
- Bottleneck
- Hub Spoke Weld & Brush Seals
Reading the bottleneck
The bottleneck is "Hub Spoke Weld & Brush Seals": it can process 67 units per day against a demand of 95 units, so it falls short of demand by 29.4%. Once downtime and scrap are counted, its cycle time grows from 614 s to 765 s, against a takt of 568 s. The largest loss at this step is equipment downtime (uptime 84%), about 117 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Electric Motors, HVAC & Heat Transfer: Electric Motors, HVAC & Heat Transfer
- Compact Brushless Industrial Servo Motor
- 800kW Magnetic-Bearing Centrifugal Chiller
- Laser-Welded 316L Plate Heat Exchanger
- Pultruded FRP Crossflow Industrial Cooling Tower
- ATEX Zone-1 Explosion-Proof 250kW Motor
- Fire-Tube Condensing 5-Ton Steam Boiler
- Commercial Heat-Recovery VRF Outdoor Unit
- Copper Foil Winding 2MVA Transformer Coil
- Microchannel V-Bank Adiabatic Air Condenser
- Pre-Fabricated District Heating Substation Skid
- Forged Stainless Steel Micro-Hydro Pelton Wheel