Laser-Welded 316L Plate Heat Exchanger

Product family: Compact Process Recuperators.

Flow: Stainless foil supplier → 4000T Hydro-Form Chevron → Robot Fiber Laser Edge Weld → Plate Cassette Tie-Bolt Press → 316L Nozzle Collar TIG → 35-Bar Helium & Hydro Test → Chemical & Food Plants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Laser-Welded 316L Plate Heat ExchangerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Stainless foil supplier → 4000T Hydro-Form Chevron (153 s) → Robot Fiber Laser Edge Weld (194 s) → Plate Cassette Tie-Bolt Press (243 s) → 316L Nozzle Collar TIG (176 s) → 35-Bar Helium & Hydro Test (135 s) → Chemical & Food Plants.SUPPLIERStainless foilsupplierI1.70 d14000T Hydro-FormChevronC/T 153 sI1.80 d2Robot Fiber LaserEdge WeldC/T 194 sI2.20 d3Plate CassetteTie-Bolt PressC/T 243 sI1.10 d4316L NozzleCollar TIGC/T 176 sI0.80 d535-Bar Helium &Hydro TestC/T 135 sI1.50 dCUSTOMERChemical & FoodPlants240 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 4000T Hydro-Form Chevron153 s35 min93%98.7%360408 (1.70 d)316
2. Robot Fiber Laser Edge Weld194 s30 min90%96.9%192432 (1.80 d)233
3. Plate Cassette Tie-Bolt Press243 s45 min84%95.5%240528 (2.20 d)169
4. 316L Nozzle Collar TIG176 s15 min94%98.3%96264 (1.10 d)272
5. 35-Bar Helium & Hydro Test135 s8 min96%99.1%48192 (0.80 d)364

Key figures

Takt time
225 s
Lead time
9.12 d
Value-added time
901 s
Process cycle efficiency (PCE)
0.18%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
240 units
Line capacity per day
169 units
Bottleneck
Plate Cassette Tie-Bolt Press

Reading the bottleneck

The bottleneck is "Plate Cassette Tie-Bolt Press": it can process 169 units per day against a demand of 240 units, so it falls short of demand by 29.4%. Once downtime and scrap are counted, its cycle time grows from 243 s to 303 s, against a takt of 225 s. The largest loss at this step is equipment downtime (uptime 84%), about 46.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.