6-Axis Collaborative Robot (Cobot) Line
Product family: Force-Sensing 12kg Cobots.
Flow: Joint-drive supplier → Carbon-Al Tube CNC Mach → Frameless Servo & Brake Fit → Joint Internal Bus Threading → Torque-Sensor Zero & Burn-In → ISO-TS 15066 Collision Test → SME Smart Factories
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Carbon-Al Tube CNC Mach | 445 s | 25 min | 94% | 98.4% | 68 | 153 (1.80 d) | 108 |
| 2. Frameless Servo & Brake Fit | 534 s | 20 min | 92% | 97.2% | 34 | 128 (1.51 d) | 85 |
| 3. Joint Internal Bus Threading | 680 s | 30 min | 85% | 94.8% | 43 | 170 (2.00 d) | 60 |
| 4. Torque-Sensor Zero & Burn-In | 483 s | 12 min | 95% | 98.0% | 21 | 85 (1.00 d) | 98 |
| 5. ISO-TS 15066 Collision Test | 368 s | 10 min | 97% | 99.1% | 13 | 59 (0.69 d) | 131 |
Key figures
- Takt time
- 635 s
- Lead time
- 8.25 d
- Value-added time
- 2,510 s
- Process cycle efficiency (PCE)
- 0.56%
- Rolled throughput yield (RTY)
- 88.1%
- Customer demand per day
- 85 units
- Line capacity per day
- 60 units
- Bottleneck
- Joint Internal Bus Threading
Reading the bottleneck
The bottleneck is "Joint Internal Bus Threading": it can process 60 units per day against a demand of 85 units, so it falls short of demand by 29.7%. Once downtime and scrap are counted, its cycle time grows from 680 s to 844 s, against a takt of 635 s. The largest loss at this step is equipment downtime (uptime 85%), about 120 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Robotics, Automation & Additive 3D: Robotics, Automation & Additive 3D
- Quad-Laser Titanium LPBF Additive Cell
- 1.5T SLAM Lidar Autonomous Mobile Robot
- End-of-Line High-Speed Robotic Palletizer Cell
- High-Speed 6m Linear Motor Pick Gantry
- IP69K Hygienic Stainless Food Delta Robot
- Scanner-Guided 6kW Remote Laser Welding Head
- EFEM Cleanroom Dual-Blade Wafer Handler
- 12-Station Servo CNC Tool Changer Turret
- High-Volume Metal Binder-Jet 3D Print Line
- AI Hyperspectral Optical Food & Plastic Sorter
- Multilevel Warehouse AS/RS Rail Shuttle