End-of-Line High-Speed Robotic Palletizer Cell

Product family: Dual-Infeed Case Palletizers.

Flow: Industrial robot-arm supplier → Guard Fencing & Baseplate → Vacuum Venturi End-Arm Tool → Infeed Belt & Safety Curtain → PLC Box & HMI Teaching → 40 Cases/Min Pattern Trial → FMCG Bottling & Food Plants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: End-of-Line High-Speed Robotic Palletizer CellSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Industrial robot-arm supplier → Guard Fencing & Baseplate (1,575 s) → Vacuum Venturi End-Arm Tool (1,890 s) → Infeed Belt & Safety Curtain (2,408 s) → PLC Box & HMI Teaching (1,710 s) → 40 Cases/Min Pattern Trial (1,305 s) → FMCG Bottling & Food Plants.SUPPLIERIndustrialrobot-armsupplierI1.83 d1Guard Fencing &BaseplateC/T 1,575 sI1.50 d2Vacuum VenturiEnd-Arm ToolC/T 1,890 sI2.00 d3Infeed Belt &Safety CurtainC/T 2,408 sI1.00 d4PLC Box & HMITeachingC/T 1,710 sI0.67 d540 Cases/MinPattern TrialC/T 1,305 sI1.17 dCUSTOMERFMCG Bottling &Food Plants12 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Guard Fencing & Baseplate1,575 s25 min94%98.4%1022 (1.83 d)15
2. Vacuum Venturi End-Arm Tool1,890 s20 min92%97.2%518 (1.50 d)11
3. Infeed Belt & Safety Curtain2,408 s30 min85%94.8%624 (2.00 d)8
4. PLC Box & HMI Teaching1,710 s12 min95%98.0%312 (1.00 d)13
5. 40 Cases/Min Pattern Trial1,305 s10 min97%99.1%28 (0.67 d)17

Key figures

Takt time
2,250 s
Lead time
8.50 d
Value-added time
8,888 s
Process cycle efficiency (PCE)
3.9%
Rolled throughput yield (RTY)
88.1%
Customer demand per day
12 units
Line capacity per day
8 units
Bottleneck
Infeed Belt & Safety Curtain

Reading the bottleneck

The bottleneck is "Infeed Belt & Safety Curtain": it can process 8 units per day against a demand of 12 units, so it falls short of demand by 34.7%. Once downtime and scrap are counted, its cycle time grows from 2,408 s to 2,988 s, against a takt of 2,250 s. The largest loss at this step is equipment downtime (uptime 85%), about 425 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.