12-Station Servo CNC Tool Changer Turret

Product family: 0.1s High-Speed Index Turrets.

Flow: Hardened 42CrMo4 Disks → Serrated Coupling 360-Tooth Grind → Live-Tooling Bevel Gear Fit → Hydraulic Clamp Piston Seal → Encoder & Coolant Manifold → 100,000-Index Repeat Bench → CNC Lathe OEMs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 12-Station Servo CNC Tool Changer TurretSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Hardened 42CrMo4 Disks → Serrated Coupling 360-Tooth Grind (504 s) → Live-Tooling Bevel Gear Fit (605 s) → Hydraulic Clamp Piston Seal (770 s) → Encoder & Coolant Manifold (547 s) → 100,000-Index Repeat Bench (418 s) → CNC Lathe OEMs.SUPPLIERHardened42CrMo4 DisksI1.80 d1Serrated Coupling360-Tooth GrindC/T 504 sI1.51 d2Live-ToolingBevel Gear FitC/T 605 sI2.00 d3Hydraulic ClampPiston SealC/T 770 sI1.00 d4Encoder & CoolantManifoldC/T 547 sI0.71 d5100,000-IndexRepeat BenchC/T 418 sI1.20 dCUSTOMERCNC Lathe OEMs75 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Serrated Coupling 360-Tooth Grind504 s25 min94%98.4%60135 (1.80 d)96
2. Live-Tooling Bevel Gear Fit605 s20 min92%97.2%30113 (1.51 d)75
3. Hydraulic Clamp Piston Seal770 s30 min85%94.8%38150 (2.00 d)53
4. Encoder & Coolant Manifold547 s12 min95%98.0%1975 (1.00 d)87
5. 100,000-Index Repeat Bench418 s10 min97%99.1%1153 (0.71 d)115

Key figures

Takt time
720 s
Lead time
8.27 d
Value-added time
2,844 s
Process cycle efficiency (PCE)
0.64%
Rolled throughput yield (RTY)
88.1%
Customer demand per day
75 units
Line capacity per day
53 units
Bottleneck
Hydraulic Clamp Piston Seal

Reading the bottleneck

The bottleneck is "Hydraulic Clamp Piston Seal": it can process 53 units per day against a demand of 75 units, so it falls short of demand by 29.6%. Once downtime and scrap are counted, its cycle time grows from 770 s to 956 s, against a takt of 720 s. The largest loss at this step is equipment downtime (uptime 85%), about 136 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.