High-Volume Metal Binder-Jet 3D Print Line
Product family: 316L/17-4PH Sintered Parts.
Flow: MIM powder supplier → Binder-Jet Piezo Layer Print → Thermal Cure Depowdering Box → Debind & Vacuum Sinter Profile → Automated Tumbling & Passivate → Archimedes Density 98.5% → Automotive & Consumer OEMs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Binder-Jet Piezo Layer Print | 60.0 s | 25 min | 94% | 98.4% | 760 | 1,710 (1.80 d) | 1,220 |
| 2. Thermal Cure Depowdering Box | 72.0 s | 20 min | 92% | 97.2% | 380 | 1,425 (1.50 d) | 969 |
| 3. Debind & Vacuum Sinter Profile | 91.0 s | 30 min | 85% | 94.8% | 475 | 1,900 (2.00 d) | 685 |
| 4. Automated Tumbling & Passivate | 65.0 s | 12 min | 95% | 98.0% | 238 | 950 (1.00 d) | 1,119 |
| 5. Archimedes Density 98.5% | 49.0 s | 10 min | 97% | 99.1% | 143 | 665 (0.70 d) | 1,511 |
Key figures
- Takt time
- 85.3 s
- Lead time
- 8.20 d
- Value-added time
- 337 s
- Process cycle efficiency (PCE)
- 0.051%
- Rolled throughput yield (RTY)
- 88.1%
- Customer demand per day
- 950 parts
- Line capacity per day
- 685 parts
- Bottleneck
- Debind & Vacuum Sinter Profile
Reading the bottleneck
The bottleneck is "Debind & Vacuum Sinter Profile": it can process 685 parts per day against a demand of 950 parts, so it falls short of demand by 27.9%. Once downtime and scrap are counted, its cycle time grows from 91.0 s to 113 s, against a takt of 85.3 s. The largest loss at this step is equipment downtime (uptime 85%), about 16.1 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Robotics, Automation & Additive 3D: Robotics, Automation & Additive 3D
- 6-Axis Collaborative Robot (Cobot) Line
- Quad-Laser Titanium LPBF Additive Cell
- 1.5T SLAM Lidar Autonomous Mobile Robot
- End-of-Line High-Speed Robotic Palletizer Cell
- High-Speed 6m Linear Motor Pick Gantry
- IP69K Hygienic Stainless Food Delta Robot
- Scanner-Guided 6kW Remote Laser Welding Head
- EFEM Cleanroom Dual-Blade Wafer Handler
- 12-Station Servo CNC Tool Changer Turret
- AI Hyperspectral Optical Food & Plastic Sorter
- Multilevel Warehouse AS/RS Rail Shuttle