High-Volume Metal Binder-Jet 3D Print Line

Product family: 316L/17-4PH Sintered Parts.

Flow: MIM powder supplier → Binder-Jet Piezo Layer Print → Thermal Cure Depowdering Box → Debind & Vacuum Sinter Profile → Automated Tumbling & Passivate → Archimedes Density 98.5% → Automotive & Consumer OEMs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: High-Volume Metal Binder-Jet 3D Print LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. MIM powder supplier → Binder-Jet Piezo Layer Print (60.0 s) → Thermal Cure Depowdering Box (72.0 s) → Debind & Vacuum Sinter Profile (91.0 s) → Automated Tumbling & Passivate (65.0 s) → Archimedes Density 98.5% (49.0 s) → Automotive & Consumer OEMs.SUPPLIERMIM powdersupplierI1.80 d1Binder-Jet PiezoLayer PrintC/T 60.0 sI1.50 d2Thermal CureDepowdering BoxC/T 72.0 sI2.00 d3Debind & VacuumSinter ProfileC/T 91.0 sI1.00 d4AutomatedTumbling &…C/T 65.0 sI0.70 d5ArchimedesDensity 98.5%C/T 49.0 sI1.20 dCUSTOMERAutomotive &Consumer OEMs950 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Binder-Jet Piezo Layer Print60.0 s25 min94%98.4%7601,710 (1.80 d)1,220
2. Thermal Cure Depowdering Box72.0 s20 min92%97.2%3801,425 (1.50 d)969
3. Debind & Vacuum Sinter Profile91.0 s30 min85%94.8%4751,900 (2.00 d)685
4. Automated Tumbling & Passivate65.0 s12 min95%98.0%238950 (1.00 d)1,119
5. Archimedes Density 98.5%49.0 s10 min97%99.1%143665 (0.70 d)1,511

Key figures

Takt time
85.3 s
Lead time
8.20 d
Value-added time
337 s
Process cycle efficiency (PCE)
0.051%
Rolled throughput yield (RTY)
88.1%
Customer demand per day
950 parts
Line capacity per day
685 parts
Bottleneck
Debind & Vacuum Sinter Profile

Reading the bottleneck

The bottleneck is "Debind & Vacuum Sinter Profile": it can process 685 parts per day against a demand of 950 parts, so it falls short of demand by 27.9%. Once downtime and scrap are counted, its cycle time grows from 91.0 s to 113 s, against a takt of 85.3 s. The largest loss at this step is equipment downtime (uptime 85%), about 16.1 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Robotics, Automation & Additive 3D: Robotics, Automation & Additive 3D