Scanner-Guided 6kW Remote Laser Welding Head

Product family: Real-Time Seam Tracking Heads.

Flow: Laser optics supplier → Sealed Optical Al Block CNC → Cleanroom Lens & Dichroic Fit → Galvo Mirror Encoder Align → OCT Seam-Track Focus Calib → 6kW Thermal Drift Beam QC → Automotive BIW Robot Cells

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Scanner-Guided 6kW Remote Laser Welding HeadSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Laser optics supplier → Sealed Optical Al Block CNC (420 s) → Cleanroom Lens & Dichroic Fit (504 s) → Galvo Mirror Encoder Align (642 s) → OCT Seam-Track Focus Calib (456 s) → 6kW Thermal Drift Beam QC (348 s) → Automotive BIW Robot Cells.SUPPLIERLaser opticssupplierI1.80 d1Sealed Optical AlBlock CNCC/T 420 sI1.51 d2Cleanroom Lens &Dichroic FitC/T 504 sI2.00 d3Galvo MirrorEncoder AlignC/T 642 sI1.00 d4OCT Seam-TrackFocus CalibC/T 456 sI0.69 d56kW Thermal DriftBeam QCC/T 348 sI1.20 dCUSTOMERAutomotive BIWRobot Cells45 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Sealed Optical Al Block CNC420 s25 min94%98.4%3681 (1.80 d)55
2. Cleanroom Lens & Dichroic Fit504 s20 min92%97.2%1868 (1.51 d)43
3. Galvo Mirror Encoder Align642 s30 min85%94.8%2390 (2.00 d)29
4. OCT Seam-Track Focus Calib456 s12 min95%98.0%1145 (1.00 d)49
5. 6kW Thermal Drift Beam QC348 s10 min97%99.1%731 (0.69 d)64

Key figures

Takt time
600 s
Lead time
8.29 d
Value-added time
2,370 s
Process cycle efficiency (PCE)
1.1%
Rolled throughput yield (RTY)
88.1%
Customer demand per day
45 units
Line capacity per day
29 units
Bottleneck
Galvo Mirror Encoder Align

Reading the bottleneck

The bottleneck is "Galvo Mirror Encoder Align": it can process 29 units per day against a demand of 45 units, so it falls short of demand by 34.5%. Once downtime and scrap are counted, its cycle time grows from 642 s to 797 s, against a takt of 600 s. The largest loss at this step is equipment downtime (uptime 85%), about 113 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.